Download Print this page

Jet JHC-200X Owner's Manual page 5

Hydraulic shop crane
Hide thumbs Also See for JHC-200X:

Advertisement

Assembly Instructions
Note: Refer to parts breakdown for part numbers found in parenthesis (#):
1. Slide short extension legs (03) into the rear support of base (01). Tighten bolts to hold in place.
2. Slide long extension legs (08) into front supports of base (01). Tighten bolts to hold in place.
3. Connect post (10) to base (01) with two M12 x 25 hex cap bolts (09) and two M12 nuts (02).
4. Attach supports (11) to base (01) and top of post (10) using three M12 x 100 hex cap bolts and three
M12 nuts (15). Tighten firmly.
5. Connect boom (13) to post (10) using one M20 x 125 hex cap bolt (14) and one M20 nut (15).
6. Slide boom extension (16) into boom (13) and fasten with one adjustment pin (26) and one hitch pin
(27).
7. Bolt lower portion of ram (21) to post (10) using one M16 x 100 hex cap bolt (17) and one M16 nut
(18).
8. Bolt upper portion of ram (21) to boom (13) using one M16 x 75 (22) hex cap bolt and one M16 nut
(18).
9. Insert small covers (28) into the short extension legs (03), long extension legs (08), and boom
extension (16). Insert big cover (29) into back end of boom (13).
Operation
1. Load to be lifted must be securely attached with slings or chain of adequate size and strength.
Before lifting the load, be sure load cannot twist, or fall from attachment.
2. Move crane into position. Legs must be extended out beyond the boom extension.
3. Close hydraulic valve at base of ram by inserting groove in handle into valve, and turning clockwise
until tight.
4. Place slings, or chains in center of hook and make sure safety latch is securely latched.
5. Slowly raise load to desired height by inserting handle into ram and pumping handle. Be careful to
note if the load wants to shift, and keep load from rotating or swinging.
6. Move load to desired location by rolling crane assembly. Use caution so that load does not swing or
rotate.
7. Carefully lower load to desired location by inserting ram handle into valve at base of ram, and slowly
turning counter-clockwise. Do not lower too quickly, and confirm load is secure once lowered fully.
5

Advertisement

loading