OP5607 Installation and Configuration

Connecting Cables

Step 1

Step 2

Step 3

Installation is simply a matter of placing the chassis on a shelf or a desktop or inserting it into a traditional rack and connecting the cables. When installing
an OP5607 in a system, it is important to have all connections completed before turning the unit on.
Connecting Cables
These are the basic cabling instructions for your OP5607. Use the cables provided to connect your devices, as instructed.
Step 1
If your OP5607 came as part of full system delivery, including an OPAL-RT simulator, simply connect the PCIe cable between the
PCIe
simulator and the OP5607 PCIe connector in the back of the unit. Make sure to connect the cable end labeled
connection
and the cable end labeled
for
OP5607-IO-
If you purchased the OP5607 as a separate unit, it is delivered with a PCIe cable and a PCIe interface board. This board must be
PCIe units
installed in your OPAL-RT simulator. Contact OPAL-RT Support for instructions to install the PCIe adaptor board in the simulator. Then
only
connect the PCIe cable from the PCIe connector at the back of the OP5607 to the simulator. Make sure to connect the cable end
labeled host to the simulator, and the cable end-labeled target to the OP5607.
If your OP5607 came configured for MuSE communication, use the SFP transceivers and LC-LC multimode fiber cable purchased with
SFP
the unit to connect one of the unit's SFP ports to one of the real-time simulator's SFP ports configured for MuSE communication.
connection
- for
Unless otherwise specified in the System Description document of your unit, any of the sixteen SFP ports can be used for MuSE
OP5607-IO-
communication.
MUSE
units only
When using SFP ports for Generic Aurora communication with other OPAL-RT units or external devices, additional SFP modules and
optical fiber cable are required.
Step 2
Connect the power cord to the unit and plug it into an appropriate power source (outlet).
Step 3
Connect the DB37 cables from the OP5607 to external devices (motor, controller, etc.). Before connecting cables, make sure that the amplitude is
compatible with the voltage ranges of the
target
to the OP5607.
OP5300 mezzanine modules
installed.
host
to the simulator,

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the OP5607 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Opal-RT OP5607

  • Page 1 OP5607. OP5607-IO- If you purchased the OP5607 as a separate unit, it is delivered with a PCIe cable and a PCIe interface board. This board must be PCIe units installed in your OPAL-RT simulator. Contact OPAL-RT Support for instructions to install the PCIe adaptor board in the simulator. Then only connect the PCIe cable from the PCIe connector at the back of the OP5607 to the simulator.
  • Page 2 Failure to do so will prevent the simulator from detecting the OP5607 FGPA during boot. If you use an SFP connection in a MuSE setup, powering up the OP5607 before the simulator is not mandatory, but it must be powered up before loading the real-time simulation.
  • Page 3 Note: Although some boards do provide a power source, using that would compromise the isolation. OPAL-RT recommends using external power source: the user must connect the power wires (provided) to either a 5 or 12 V power source. Make sure that the Vuser source switch on the loopback board is set to “External”.

Table of Contents