System Operation; Initial Comissioning Procedure - YASKAWA PVS-500 User Manual

Dc-coupled storage system
Table of Contents

Advertisement

4. System Operation

Following the installation of all equipment and confirmation of all connections and
terminations, system commissioning should commence.
4.1

Initial Comissioning Procedure

 Turn OFF and lock out all PV Combiner Boxes
 Turn OFF and lock out AC source to AC Combiner
 Turn OFF and lock out battery source
 Turn OFF all three of the XGI-1500 red on/off switches on the right side of an inverter.
 Press the DPS 500 emergency OFF (EPO) button on the front panel of the converter.
 Turn the disconnect handle on the AC combiner to the OFF position
 Turn OFF all 5 DC disconnect switches on the front of the DC Recombiner
 Turn OFF the DC disconnect switches on the DCP 500 converter.
 Remove DC Recombiner cover and verify absence of voltage from all sources
 Verify all cabling in the DC recombiner is installed correctly and torqued appropriately
 Replace DC recombiner cover
 Remove AC Recombiner cover and verify absence of voltage from all sources
 Verify all cabling in the AC Combiner is installed correctly and torqued appropriately
 Replace DC combiner cover
 Close all PV source circuit fuse holders in the combiner boxes and close the cover.
 Energize the Battery
 Turn ON source of power to the AC combiner
 Turn the DC disconnect switches on the DCP 500 converter to the ON position.
 At each combiner, turn the DC disconnect to the ON position.
 Turn ON all 5 DC disconnect switches on the front of the DC Recombiner
 Turn the disconnect handle on the AC combiner to the ON position
 Release the DPS 500 emergency off (EPO) button on the front panel of the converter.
 Turn ON all three of the XGI-1500 red on/off switches on the right side of an inverter.
 Logon to the network and confirm network access to inverters and Heila controller.
Yaskawa Solectria Solar
DOCR-071069
Page 21 of 24