4. System Operation
Following the installation of all equipment and confirmation of all connections and terminations, system
commissioning should commence.
Initial Commissioning Procedure
Turn OFF and lock out AC source to AC Combiner
Turn OFF and lock out battery source
Turn OFF all three of the XGI-1500 red on/off switches on the right side of the inverter
Turn the disconnect handle on the AC combiner to the OFF position
Remove DC De-Combiner cover and verify absence of voltage from all sources
Verify all cabling in the DC De-Combiner is installed correctly and torqued appropriately
Replace DC De-Combiner cover
Remove AC Combiner cover and verify absence of voltage from all sources
Verify all cabling in the AC Combiner is installed correctly and torqued appropriately
Replace AC Combiner cover
Open all three inverter covers, one by one
Check for moisture on all internal surfaces. If moisture is found, remove all standing water and
condensation where accessible.
Leave covers off and allow all condensation to be dried by the environment. Once fully dried,
wait at least an additional 1/2hr before re-installing covers.
Close all three inverter covers
Turn ON source of power to the AC combiner
Turn the disconnect handle on the AC combiner to the ON position
Turn ON all three of the XGI-1500 red on/off switches on the right side of the inverter, in any
order.
Energize the battery, according to its instructions
Using a laptop, log on to the network and confirm network access to inverters and PMC
controller. Please consult the PMC's manual on how to perform this step.
Conduct a test run (charge/discharge) of the battery system
Yaskawa Solectria Solar
DOCR-071070