Commissioning
3.3

Commissioning after taking out of operation

If present
Remove cover plates (blind flanges) on the compressor casing, on the gas-inlet as well as
on the gas-outlet.
Remove the screw plugs on the water connections and fit the water pipe.
Version with compressor wheel cooling:
Remove the screw plug on the cooling air connection and fit the cooling air line.
General
Check the exhaust gas pipe before and after the turbine for combustion residues or water
residues and clean it. Remove any foreign objects that may be present.
Check and clean filter silencer or air supply line, and remove any foreign objects that may
be present.
Put engine-side oil circulation to the turbocharger into operation.
Prepare the turbocharger for operation according to section "Checks before
commissioning".
The turbocharger is now ready for operation.
© Copyright 2015 ABB. All rights reserved.
HZTL4030_EN
Page 27 / 115
Revision C
September 2015

Advertisement

Table of Contents
loading

This manual is also suitable for:

A140-h56

Table of Contents