Thank you for purchasing a Sealey product. Manufactured to a high standard this product will, if used according to these instructions
and properly maintained, give you years of trouble free performance.
IMPORTANT: PLEASE READ THESE INSTRUCTIONS CAREFULLY. NOTE THE SAFE OPERATIONAL REQUIREMENTS, WARNINGS & CAUTIONS.
USE THE PRODUCT CORRECTLY AND WITH CARE FOR THE PURPOSE FOR WHICH IT IS INTENDED. FAILURE TO DO SO MAY CAUSE DAMAGE
AND/OR PERSONAL INJURY AND WILL INVALIDATE THE WARRANTY. PLEASE KEEP INSTRUCTIONS SAFE FOR FUTURE USE.
1. SAFETY INSTRUCTIONS
Keep crane, and lifting slings, supports and beams in good working order and condition. Follow the inspection requirements as described
3
in Section 5. Take immediate action to repair or replace damaged parts by contacting your supplier. Ensure that all accessory lifting
devices are suitably certified. If crane is damaged immediately remove from service.
Ensure the surface on which the crane is used is level and firm, being capable of sustaining the crane and the maximum load.
3
Never use crane on tarmacadam or on soft surfaces.
7
Ensure that the crane legs and arms are always locked before use, and jib extension is locked in fixed jib position by means of the lock split pin.
3
Keep children and unauthorised persons away from the work area.
3
Keep work area clean and tidy and free from unrelated materials, and ensure that there is adequate lighting.
3
Ensure that load does not exceed the maximum lifting capacity. Overloading the crane is dangerous. Where appropriate, use only
3
the lifting points recommended by the manufacturer of the item to be lifted, i.e. vehicle engine.
Before lifting the load ensure that the crane jib is in the lowest possible position, that there are no obstacles which may snag the load
3
whilst it is being lifted and that the area above the jib is clear.
DO NOT apply any sideways pressure to the crane during lifting or suspension of load.
7
To avoid injury, be fully aware of your own and other persons locations in relation to the lifting and lowering of the load.
3
Keep a sound footing and balance, and ensure that the floor is not slippery. Wear non-slip shoes.
3
Ensure the centre of gravity of the load always remains inside the crane base.
3
DO NOT attempt to lift the load at an angle, and do not allow the load to swing during lifting.
7
DO NOT allow the load to drop suddenly. Lower load with care and ensure that you are fully aware of the condition of the surface onto
7
which the load is to be lowered.
DO NOT load beyond rated capacity for each specified jib position as indicated in Section 2. The capacity reduces as the jib is extended.
7
DO NOT position any part of your body beneath the load, and do not climb on the crane.
7
DO NOT use the crane to move or transport a load around the workshop. The crane is a lifting device only.
7
DO NOT attempt to adjust the safety valve, as this has been set and sealed by the manufacturer.
7
DO NOT use the crane for a task it is not designed to perform.
7
DO NOT use whilst under the influence of drugs, alcohol or intoxicating medication or when tired.
7
When not in use, store the crane in a safe, dry, childproof, area.
3
WARNING: Failure to heed safety and warning instructions may result in damage and/or personal injury and will invalidate the warranty.
p
p
2. SPECIFICATIONS
Max. lift @ min. jib extension: kg . . . . . . . .500
Max. lift @ max. jib extension: kg . . . . . . . .200
Max. jib height: mm . . . . . . . . . . . . . . . . . . . . . . .2100
Overall height . . . . . . . . . . . . . . . . . . . . . .1570
Frame length (max): mm . . . . . . . . . . . . .1570
Width of frame (max): mm . . . . . . . . . . . . .970
Width inside frame (max): mm . . . . . . . . . .770
Max. height of leg section from floor: mm. .140
Distance between base wheel centres: mm
Weight: kg . . . . . . . . . . . . . . . . . . . . . . . . . 92
3. ASSEMBLY INSTRUCTIONS
Your crane is delivered assembled but in a folded condition. Before using it is necessary to lay the folded crane on its ‘back’ on the floor
and proceed as follows.
3.1.
Lower the crane legs. Lock them in place with the pins and split pins.
3.2.
Rotate the assembled crane onto its wheels.
3.3.
Open the valve at top of ram by turning to left and pump 10-20 times. This will purge any air that may have entered during transit.
3.4.
Pull crane jib up slightly, close valve and pump the handle. The jib will now rise. Pump the jib all the way up once and lower it again (this
will check the oil level).
3.5.
Crane is now ready. Ensure that it is complete and not damaged. If you experience any problems contact your supplier immediately.
4. OPERATING INSTRUCTIONS
WARNING! Ensure that you read, understand and apply Section 1 safety instructions, and that parts 3.3 and 3.4 have been
p
p
successfully performed before using the crane.
4.1.
Pump the handle to raise the jib to the appropriate height at which the load may be secured.
4.2.
Select the required jib extension by removing the jib locking pin, extending as desired (up to a maximum of 1.3mtr) and replace the pin.
Note: Ensure the jib locking pin is replaced correctly i.e. completely through the jib and jib extension where the holes align,
thereby locking the extension safely in place.
4.3.
Connect the crane hook to the load using a suitable certified sling or support beam. Ensure that you are aware of the load weight
and check that it is within the capacity of the crane at the jib extension you are using. When removing engines ensure that you know
the engine weight. Use only lifting points recommended by the vehicle manufacturer.
4.4.
Lift only from directly above the load.
. . . 370
p WARNING! DO NOT LIFT THE LOAD AT AN ANGLE!
INSTRUCTIONS FOR:
FOLDING CRANE
500KC.V2
Model:
Lifting capacity, Position 1: kg . . . . . .500
Lifting capacity, Position 2: kg . . . . . .400
Lifting capacity, Position 3: kg . . . . . .300
Lifting capacity, Position 4: kg . . . . . .200
Length of jib, Position 1: mm . . . . . .1000
Length of jib, Position 2: mm . . . . . .1100
Length of jib, Position 3: mm . . . . . .1200
Length of jib, Position 4: mm . . . . . .1300
500KC.V2 - 2 - 230703

Advertisement

loading

Summary of Contents for Sealey 500KC.V2

  • Page 1 500KC.V2 Model: Thank you for purchasing a Sealey product. Manufactured to a high standard this product will, if used according to these instructions and properly maintained, give you years of trouble free performance. IMPORTANT: PLEASE READ THESE INSTRUCTIONS CAREFULLY. NOTE THE SAFE OPERATIONAL REQUIREMENTS, WARNINGS & CAUTIONS.
  • Page 2 5.2.2. The ram is filled with oil and should only require occasional topping up. DO NOT use brake fluid, as this will damage the hydraulic seals. a) Use only good quality hydraulic jack oil available from your Sealey dealer. b) Fully lower the jib extension arm.