6. Install the insulation per the insulation manufacturer's
installation instructions.
NOTE: Pipe length (ft / M) specified for maximum pipe lengths
located in unconditioned spaces (See Table 16) cannot exceed
total allowable pipe length as calculated from Table 14.
Configure the Furnace
WARNING
!
CARBON MONOXIDE POISONING HAZARD
Failure to follow this warning could result in personal injury or
death.
To route the vent pipe and combustion air pipe through the
furnace, the manufacturer supplied kit must be used. Failure
to properly seal the blower compartment from the furnace
vestibule could result in the circulation of carbon monoxide
throughout the structure. The vent pipe and combustion air
pipe must be a continuous pipe while passing through the
blower compartment. Seals supplied in this kit must be
installed per the instructions provided. Follow all procedures
outlined in these instructions.
Near Furnace Vent Connections
Offsets in the vertical portion of the vent pipe should be made
with 45 degree elbows instead of 90 degree elbows. Short
horizontal runs of vent pipe are difficult to pitch correctly and
may trap water in the vent pipe.
Trapped water in the vent pipe may result in nuisance pressure
switch tripping.
Figure 53
Near Furnace Vent Connections
Avoid short horizontal offsets with 90
deg. Elbows. Short offsets can be
difficult to slope and may trap con-
densate.
Slope vent pipe back to the
furnace at least ¼" per foot
44
Use 45 deg. Elbows where
possible, to ensure conden-
sate drainage.
L14F020A
L14F020B
Specifications subject to change without notice.
Install the Vent and Combustion Air Pipes
With the furnace installed in the required position, remove the
desired knockouts from the casing. It will be necessary to
remove one knockout for the vent pipe and the other knockout
for the combustion air connection. (See Figure 12)
Use a flat blade screwdriver and tap on the knockout on
opposite sides, where the knockout meets the casing. Fold the
knockout down with duct pliers and work the knockout back
and forth until it is removed. Trim any excess metal from the
knockout with tin snips.
The vent elbow can be rotated to the required location on the
casing if necessary. See Figure 54 to rotate the vent elbow:
1. Loosen the clamp on the inlet of the vent elbow attached
to the inducer.
2. Rotate the vent elbow to the required position. There are
rounded notches in the vent elbow to align it with the
inducer for each orientation.
3. Tighten the clamp around the vent elbow. Torque the
clamp to 15 lb-in. See Figure 55 through Figure 58.
Figure 54
Inducer Vent Elbow − PSC
INDUCER OUTLET
INDUCER OUTLET CHOKE
40,000 BTUH MODELS WITH 10 FT. (3.1 M) OF VENT OR LESS
Gas Furnace: (F/G)9MVE
PSC INDUCER ASSEMBLY
A13075A
VENT ELBOW CL AMP
TORQUE 15 LB−IN.
VENT PIPE CL AM
TORQUE 15 LB−IN
VENT ELBOW
A14277
440 01 4401 02