System layout SYSTEM LAYOUT 1195 1144 Ventilation holes Collector Collector return outlet Collector probe socket Direction of flow of Glass 3,2 mm heat transfer liquid Connection ring nut, 1" Connector Ø 22 mm Identification IDENTIFICATION Data label Data plate Code To be applied to the back of CODICE : 20091462 the solar collector on installation...
Technical specifications TECHNICAL SPECIFICATIONS DESCRIPTION Total area 2,30 Exposed area 2,16 Effective absorption area 2,15 Connections (M) - (F) 1" Empty weight 40,0 Liquid content Recommended flow rate for each line per m of collector l/(h x m Minimum flow rate for each line per m of collector l/(h x m Maximum flow rate for each line per m...
Connections CONNECTIONS When tightening a fitting, HOLD THE OPPOSITE FITTING STEADY WITH A SECOND TOOL to avoid damage Collectors in the same line must be connected so that the heat transfer fluid flows through them in series. The pipe to the heat exchanger in the storage cylinder must be connected to the outlet with the temperature sensor socket on the last collector in the line (see figure).
Unpacking the product UNPACKING THE PRODUCT The solar collectors are packed in various ways depending on the number of units supplied: A Packages of 1 or 2 collectors B Packages of 5 collectors Pallet contents: - collector - document envelopes containing instruction manual, bar code labels and data label.
Installation INSTALLATION Solar collectors must be installed with the correct Angle of collectors / General mounting kit (which includes all necessary rails and Solar collectors are designed to be installed at angles of brackets) as listed in the Catalogue. between 15° (minimum) and 75° (maximum). Make sure that the bleed and vent valves of the collectors remain open while the collectors are being installed.
Filling the circuit FILLING THE CIRCUIT Perform the following steps before starting up the system. 1 - FLUSHING AND SEAL TESTING THE SYSTEM If copper piping has been used and joints have been hot brazed, flush out the system to remove any brazing resi- dues.
Pressure at boiler up to 15 m 3 bar 15 - 20 m 3,5 bar 20 - 25 m 4 bar 25 - 30 m 4,5 bar General rule: p [bar] = 1.5 + H [m] / 10 Checks CHECKS On completion of the installation, perform the checks listed in the table below.
Page 12
Commercial Offices: Via Risorgimento, 23 A 23900 - Lecco www.berettaboilers.com Beretta reserves the right to modify the characteristics and specifications given in this publication at any time and without prior notice as part of its policy of continuous product improvement.
Need help?
Do you have a question about the SCF-25B and is the answer not in the manual?
Questions and answers