5. SWITCH-ON

5.1
Only appropriately qualified personnel should switch-on the fan. Before switching on confirm that
the electrical supply is fully compliant with the requirement of the product as detailed on the motor
nameplate, that the product is correctly installed, all component parts and fixings are secure, safety
guards are in place and no loose items are present in the vicinity of the box fan.
5.2
Immediately after switch-on we recommend that the product is checked for smooth, low-vibration
running, that the current consumption is within the full load current specified on the nameplate, and that
the motor is not getting excessively hot. Check that the impeller is rotating in the correct direction. The
box fan must not be switched on and off in a manner that could cause overheating of the motor, and
could damage the insulation of the motor and the internal wiring to the motor.

6. MAINTENANCE

CAUTION
6.1
6.2
It is essential to ensure that all fixings on the product are secure.
6.3
The complete fan/motor assembly can be easily removed for cleaning purposes. Fans should be
disconnected from the controller prior to removal. Under no circumstances should the interior space and
fan unit be cleaned with water or high-pressure steam.
Fig. 3-Remove lid to access fans
6.4
After maintenance ensure that no loose items are present in the vicinity of the fan, that all safety guards,
chains, drop rods etc, are properly secured into their original location, and that any temporary device used
to stop the fan impeller rotating has been removed.
6.5
Information on all aspects of overhaul/extended maintenance is available from Woods Air Movement
service centre. After overhaul/extended maintenance the box fan must be safely and correctly installed
back into its original position in accordance with this document.
6
No maintenance work should be attempted before switching off and completely isolating
the product and its controls from all electrical supplies. Also allow the rotating parts of
the fans to come to rest and the motors to cool.
Fig. 4 - Remove bellmouth first, then unscrew motor