Startup and Test

Before turning on the unit, the following checks are to be performed by Qualified Personnel.
L1, L2, and L3 are connected to the three-phase input power.
T1, T2, and T3 are connected to the motor.
The three-phase input voltage is within the ASD setup tolerances.
There are no shorts and all grounds are secured.
With the previous checks confirmed, ensure that the direction of the motor rotation in the Bypass
mode and in the ASD-driven mode is consistent.
Ensure that all personnel are clear of the motor and the motor-driven equipment.