COOLING-ONLY PROCEDURE
NOTE: If superheat- or subcooling-charging conditions are not
favorable, charge must be weighed in accordance with unit-rating
plate ±0.6 oz/ft of 3/8-in. liquid line above or below 15 ft
respectively.
EXAMPLE:
To calculate additional charge required for a 25-ft line set:
25 ft – 15 ft = 10 ft X 0.6 oz/ft = 6 oz of additional charge
HEATING CHECK-CHART PROCEDURE
To check system operation during heating cycle, refer to the
Heating Check Chart on outdoor unit. This chart indicates whether
a correct relationship exists between system operating pressure and
air temperature entering indoor and outdoor units. If pressure and
temperature do not match on chart, system-refrigerant charge may
not be correct. Do not use chart to adjust refrigerant charge.
NOTE: When charging is necessary during heating season,
charge must be weighed in accordance with unit rating plate ±0.6
oz/ft of 3/8-in. liquid line above or below 15 ft respectively.
Step 14—Final Checks
IMPORTANT: Before leaving job, be sure to do the following:
1. Securely fasten all panels and covers.
2. Tighten service valve-stem caps to 1/12-turn past finger-tight.
3. Leave User's Manual with owner. Explain system operation
and periodic maintenance requirements outlined in manual.
4. Fill out Dealer Installation Checklist and place in customer
file.
Table 2—Phase-Monitor LED Indicators
LED
OFF
FLASHING
ON
Fig. 7—Phase-Monitor Control
5
A00010
STATUS
No call for compressor
operation
Reversed phase
Normal