PP30 Gasifier-Engine Startup For a list of all parts of the Power Pallet including a list of parts, definitions and all other useful information see the PP30 Component Reference document Collect the following items 1. ½” NPT Pipe tee for lighting port 2.
Page 2
Image Set 1 Image 2 Using a propane torch, light the ACV char in pipe tee (Image Set 3) When char is glowing, slowly open the flare valve, letting the embers be sucked into the 2 of 5 FILE-004468 PP30 Gasifier-Engine Startup...
Page 3
Increase the air blower to 7 and continue to adjust to maintain a strong roaring sound from the flare to allow the reactor to reach full operating temperature. This can take 10-15 minutes 3 of 5 FILE-004468 PP30 Gasifier-Engine Startup...
Page 4
(PCU - temperature at the reduction zone) is greater than 300°C, the engine can be started by the following steps (note: while the engine can be started at lower values, the PP30 system will accumulate more tar and require more maintenance) Power Generation Supersystem...
Page 5
Generator Available Contactor Closed Power Export GASIFIER-ENGINE STARTUP PROCEDURE COMPLETE 5 of 5 FILE-004468 PP30 Gasifier-Engine Startup...