PIPE CONNECTIONS BETWEEN INDOOR AND OUTDOOR UNIT

26
PIPE CONNECTIONS BETWEEN INDOOR AND
OUTDOOR UNIT
- Pipe connections can be done on the front side or on the side according to the installation envi-
ronments.
- Be sure to let 0.2kgf/cm2 Nitrogen flow in the pipe when welding.
- If Nitrogen was not flown during welding, many oxidized membranes may form inside the pipe
and disturb the normal operations of valves and condensers.
Left Side Pipe
Draw Out
Front Pipe Draw Out

Preparation Work

- Use Knock Outs of Base Pan of the outdoor unit for Left/Right or Bottom pipe drawing outs.
CAUTION
!
• Do not give damage to the pipe/base during the Knock Out work.
• Proceed to pipe work after removing burr after Knock Out work.
• Perform sleeve work to prevent damage to the wire when connecting wires using knock
Outs.
Right Side Pipe
Draw Out
Removal Area for Liquid/Gas pipe
bottom side connections.
Regulator
Refrigerant Pipe
Nitrogen
Nitrogen
Nitrogen
Direction
Direction
Direction
Taping
Valve
Nitrogen