Royal Well Slim Kweken Louvre Quick Start Manual

Advertisement

Montagehandleiding / Instructions de montage /
For the louver assembly you will need 1 top sill, 1 bottom sill, 2 side jambs (one with han-
Montageanleitung / Manual
dle), 4 self-tapping screws, 4 crop head bolts and nuts and glass blades .
Louver Assembly Instruction
Louvre
jamb1
6 L, 610 W x 610 H mm, blank
Size
526
6 L, 610 W x 610 H mm, groen gecoat
For the louver assembly you will need 1 top sill, 1 bottom sill, 2 side jambs (one with han-
dle), 4 self-tapping screws, 4 crop head bolts and nuts and glass blades .
QTY
1
6 L, 610 W x 610 H mm, zwart gecoat
Procedure:
A1
jamb1

1. Installation of Louver frame

Place the top sill into position on side jamb of louver and secure with self tapping screws.
Size
567
Do the same on the other top corner.
Size
526
in mm
Do the same with bottom sill.
Please note that the handle is on the right hand side. The diagrams are viewed from in-
QTY
1
side.
Procedure:
1. Installation of Louver frame
Place the top sill into position on side jamb of louver and secure with self tapping screws.
Do the same on the other top corner.
Do the same with bottom sill.
Please note that the handle is on the right hand side. The diagrams are viewed from in-
side.
INSTALLEREN / INSTALLER / INSTALLIEREN / INSTALLATION
• Vanuit de binnenkant bekeken hoort de handgreep aan de rechterkant

2. Installation of louver to the structure

NL
• Plaats het profiel B in op de zijprofielen A1 + A2 en zet ze vast met zelftappende schroeven
The louver is fitted after the unit is assembled fully and during glazing.
• Doe hetzelfde met de onderdorpel
The louver is fitted to the vertical glazing bar/wall utilizing either 4 unoccupied bolts previously
• Plaats het louvre frame tussen 2 ruiten of tussen de grond ligger en een ruit
inserted, or the 4 crop head bolts supplied with the louver kit.
• Bevestig het louvre frame aan de kasroeden met behulp van hamerkopbouten en moeren
The louver is fitted from inside the structure with the angle jams fitting around the vertical
• Vu de l'intérieur, la poignée doit être à droite
F
greenhouse bars concerned.
• Placez le profilé B sur les profilés latéraux A1 + A2 et fixez-le avec des vis autotaraudeuses
• Faites de même avec le seuil
The louver handle is on the inside of the greenhouse and is fitted to the right of the louver ( as
• Placez le cadre de la grille entre 2 fenêtres ou entre le sol et une fenêtre
viewed from the inside)
• Fixez le cadre de la grille aux barres de la serre à l'aide de vis à tête marteau et d'écrous
First you should locate where to fit the louver. In that case it will be necessary to cut the glass
• Von innen gesehen sollte sich der Griff rechts befinden
2. Installation of louver to the structure
D
either above or below the position in which you decide to local the unit.
• Profil B auf die Seitenprofile A1 + A2 legen und mit Blechschrauben befestigen
The louver is fitted after the unit is assembled fully and during glazing.
• Machen Sie dasselbe mit der Schwelle
The louver is fitted to the vertical glazing bar/wall utilizing either 4 unoccupied bolts previously
• Platzieren Sie den Lamellenrahmen zwischen 2 Fenstern oder zwischen dem Bodenträger und einem Fenster
inserted, or the 4 crop head bolts supplied with the louver kit.
• Befestigen Sie den Lamellenrahmen mit Hammerkopfschrauben und Muttern an den Gewächshausstangen
The louver is fitted from inside the structure with the angle jams fitting around the vertical
• Viewed from the inside, the handle should be on the right
GB
greenhouse bars concerned.
• Place profile B on side profiles A1 + A2 and secure with self-tapping screws
• Do the same with the sill
The louver handle is on the inside of the greenhouse and is fitted to the right of the louver ( as
• Place the louvre frame between 2 glass panes or between the ground girder and a glass pane
viewed from the inside)
• Attach the louvre frame to the greenhouse bars using hammer-head bolts and nuts
First you should locate where to fit the louver. In that case it will be necessary to cut the glass
either above or below the position in which you decide to local the unit.
jamb2
sill
526
592
1
2
A2
B
jamb2
sill
567
526
592
1
2
B
Top sill
A1
Side jamb
Top sill
Side jamb
— 526x592 mm
RW0254
M6x10
Φ3.5x19
Crop
4
4
M6x10
Φ3.5x19
Hamerkop
Crop
4
4
B
A1
1
Glass
M6
573x100
RW2591
4
6
RW2592
Glass
M6
573x100
4
6
A2
B
Binnen aanzicht / Vue intérieure /
Innenansicht / View from inside

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Slim Kweken Louvre and is the answer not in the manual?

Questions and answers

Summary of Contents for Royal Well Slim Kweken Louvre

  • Page 1 Montagehandleiding / Instructions de montage / For the louver assembly you will need 1 top sill, 1 bottom sill, 2 side jambs (one with han- Montageanleitung / Manual dle), 4 self-tapping screws, 4 crop head bolts and nuts and glass blades . Louver Assembly Instruction Louvre jamb1...
  • Page 2 Place the louver frame under the top panel of glass. The bottom sill of the louver should rest Place the louver frame under the top panel of glass. The bottom sill of the louver should rest * * on the lower glass panel or the base framing of the greenhouse. on the lower glass panel or the base framing of the greenhouse.

Table of Contents