Page 2
1. Install the 15 modules (3.9kWh) on the Rack properly. Fix and tighten properly with screw provided. 2. Install and fit the LCD Monitor on the Rack designed hole and fix with the screw provided. 3. Fix the Circuit breaker on the rack with the screw provided. 4.
Page 3
Cables from SIRIUS MODULE Cables going to ENERGY SERVER 5. Connect the 15 modules (3.9kWh) in series connection. 6. Two end cables (positive and negative) will be connected to the Circuit breaker (load side).
Page 5
8. Switch on PC and computer for monitoring the modules. 9. Switch on the modules by Switching on circuit breaker (modules backside)and press the fault reset button to activate the terminals Cables from SIRIUS MODULE Cables going to ENERGY SERVER...