BEFORE INSTALLATION
Read these instructions carefully before installing and commissioning the cleanroom monitor. Failure
to follow these instructions may result in product damage. Do not use in an explosive or hazardous
environment, with combustible or flammable gases, as a safety or emergency stop device or in any
other application where failure of the product could result in personal injury. Take electrostatic discharge
precautions during installation and do not exceed the device ratings.
MOUNTING
STEP 1 - As illustrated in Figure 1, unscrew four screws
from faceplate, set screws aside, and remove faceplate
from mounting bracket.
Cut hole in wall 210 mm x 167 mm
high. Ensure unit can be secured to
wall stud or equivalent on at least
two sides.
STEP 2 - As illustrated in Figure 2, feed wires through
mounting bracket and conduit connector/cable gland and
secure.
STEP3 - As illustrated in Figure 3, insert mounting bracket
into hole in wall.
Figure 2
Figure 2
IN-CR3CXXNET-01
04/20
Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com
INTRODUCTION
The CR3 Series Cleanroom Monitor was developed specifically
to allow for monitoring of confined spaces with accuracy and
reliability.
The CR3C features analog inputs for connecting remote sensors
for monitoring temperature, humidity and pressure (remote
sensors not included). The CR3C is available with output signal
of either Analog, BACnet ® or Modbus. Standard features include
adjustable alarm relays for each parameter, audible/visual alarms,
and large LED displays.
The CR3C is housed in a flush fitting stainless-steel front plate that
enables the user to wipe down the unit when necessary.
210 mm
CLEANROOM MONITOR
CR3C Network - Installation Instructions
Figure 1
Figure 1
Figure 3
Figure 3
Page 1

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the CR3 Series and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Greystone Energy Systems CR3 Series

  • Page 1 STEP3 - As illustrated in Figure 3, insert mounting bracket into hole in wall. Figure 2 Figure 2 Figure 3 Figure 3 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com Page 1...
  • Page 2 For end of Line (EOL) device place termination resister jumper in ON position, for all other devices, place jumper in OFF position. Page 2 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 3 Connect Shield One End Only Figure 12 CONNECTORS (Front view, screw on top) ALARM CONTACTS ANALOG OUTPUTS COMMS DP/TE/RH IN DIG IN Page 3 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 4: Alarm Relays

    If the alarm condition is reset and then set again, the buzzer will activate again. The buzzer provides a “beeping” or “chirping” sound, not a continuous tone. Page 4 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 5: Digital Input

    Installer Menu items such as TEMP DISPLAY. Display brightness may be changed from high to low using DISPLAY BRIGHTNESS via the User Menu. Page 5 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 6: Operation

    2. Address 0-127 for BACnet® Addr b a c 1-255 for Modbus 0 to 255 0 0 3 Page 6 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 7 10. AO RH Override 0 to 100 (Default = 0) 11. AO DP Override a o 3 0 to 100 (Default = 0) Page 7 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 8 7. RH Alarm High Setpoint (Resolution is 1 %RH via the menu) r h s p 40 to 90% RH Page 8 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 9 Note that the setpoint resolution is limited when setting with the menu, but higher resolution is available via the network. Page 9 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 10: Specifications

    7 segment red LED, 0.80” (20.32 mm) high Alarm Indication Low/High alarm red LED for each DIMENSIONS 36mm 225 mm 1.46“ 8.86“ 182.5 mm 7.19“ Page 10 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 11: Bacnet® Protocol

    BACnet® and Modbus setup guide downloads are available online. BACNET® PROTOCOL http://downloads.greystoneenergy.com/SG/SG-CR3-Bacnet-01.pdf MODBUS PROTOCOL http://downloads.greystoneenergy.com/SG/SG-CR3-Modbus-01.pdf Page 11 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...
  • Page 12 Page 12 IN-CR3CXXNET-01 04/20 Copyright © Greystone Energy Systems, Inc. All Rights Reserved Phone: +1 506 853 3057 Web: www.greystoneenergy.com...

This manual is also suitable for:

Cr3c network

Table of Contents