Inspection and Start-up Checklists

Receiving and Inspecting

 Unit received undamaged
 Unit received complete as ordered including accessories

Handling and Installing

 Unit mounted on solid level surface
 Sufficient space allowed for access to unit and accessories. Proper electrical service
provided
 Hot water provided to humidifier
 Drain lines and trap installed properly
 Ductwork, fittings and grilles installed properly
 All cold duct surfaces insulated
 Low ambient control included if freezing condition present. No obstructions to air
flow to condenser

Starting-up the Unit

 General visual inspection looks good. All wiring connections checked
 All ducts, grilles and panels in place
 Start unit
 Check ducts and connections for air leaks
 Balance air distribution
 Confirm condenser airflow is unrestricted
 Verify cooling and heating operation
 Check for excessive noise or vibration