Commissioning and adjustment

1. Remove the neutralising system
cover.
2. For part no. 7437829: Assemble
the slot-together casing. The size of
the fill area for neutralising granu-
late can be determined subject to
the condensate level (see
page 10).
3. Fill the relevant area with neutralis-
ing granulate (see pages 8
to 10).
4. Fill the neutralising system with
water.
6
(cont.)
3. Route the drain hose from the neu-
tralising system to the drainage
system with a fall. Secure the hose
with hose clips.
Note
■ Never connect the drain hose
directly to the sewage system. To
avoid retrograde bacterial con-
tamination from the sewage sys-
tem, observe the minimum clear-
ance of 20 mm (see diagram).
■ Never step on the hose. Protect
the hose against mechanical
damage.
5. Check the container and the supply
and drain lines for leaks.
6. Close the neutralising system
cover.
7. Start the heat source.
8. Record commissioning on
page 17.
Note
During commissioning, instruct the sys-
tem user in the operation of the appli-
ance.