Ensure adequate lifting equipment is available for unloading and moving
the compressor to the installation site.
NOTICE
Lifting equipment must be properly rated for the weight of the
unit.
Lift the unit by the shipping skid only. Use straps to prevent
tipping.
CAUTION
Do not work on or walk under the compressor while it is
suspended.
Before signing the delivery receipt, inspect for damage and missing parts.
If damage or missing parts are apparent, make the appropriate notation on
the delivery receipt, then sign the receipt. Immediately contact the carrier
for an inspection. All material must be held in the receiving location for
the carrier's inspection. Delivery receipts that have been signed without a
notation of damage or missing parts are considered to be delivered "clear. '
Subsequent claims are then considered to be concealed damage claims.
Settle damage claims directly with the transportation company.
HYD-7-610
RECEIPT & INSPECTION
If you discover damage after receiving the unit (concealed damage), the
carrier must be notified within 15 days of receipt and an inspection must
be requested by telephone with confirmation in writing. On concealed
damage claims, the burden of establishing that the unit was damaged in
transit reverts back to the claimant.
Read the unit specification label to verify that it is the model ordered.