Baxi 100/2 HE Plus Installation & Servicing Instructions Manual page 31

Wall mounted powered flue condensing boiler, gas fired central heating unit
Table of Contents

Advertisement

Flue Sampling Point
Injector Pipe
Injector Pipe Retaining
Screw
Protection
Sensor Leads
Fig. 42
Wing Nuts
Central Insulation Panel
Burner
Combustion
Box Base
Heat Exchanger
Support Bracket
Combustion Box Base
Securing Screws
Burner Securing
Screws
Fig. 44
Fig. 41a
Securing Nut
Fan
Sensor
Leads
Electrical Supply
Condensate
Trap
Lock Nut
Condensate
Drain Pipe
Fig. 43
12.0
Servicing the Boiler
12.1
Annual Servicing (Cont)
10. To clean the heat exchanger and burner proceed
as follows:
a) Disconnect the electrical leads to the fan
component protection sensor (Fig. 42).
b) Loosen the screw retaining the gas injector pipe at
the venturi (Fig. 42).
c) Undo the two wing nuts to disconnect the fan
(Fig. 42).
d) Remove the fan and disconnect the electrical supply
to it (Fig. 42).
e) Remove the gas injector pipe from the gas valve
(push-fit) (Fig. 42).
f) Undo the condensate trap securing nut, lock nut and
the condensate drain pipe. Remove the condensate
trap and disconnect the sensor leads (Fig. 43).
g) Remove the two screws securing the burner and
remove the burner. Visually inspect the internal burner
baffle for obstruction, check seal around baffle for
cracks/damage. Clean with a soft brush.
h) Loosen the two screws retaining the heat exchanger
support bracket and slide to the left to remove
(Fig. 44).
i) Remove the four screws securing the heat
exchanger/combustion box base and withdraw the
base.
j) Lower the central insulation panel and check
condition (Fig. 44). Replace the lower insulation pad if
Service Drain
necessary.
Plug
k) Ensure the heat exchanger fins are clear of any
obstruction.
l) Check condition of all seals. Important: Pay
particular attention to the condition of the
combustion box door seals.
m) Reassemble in reverse order and check for leaks.
11. Check CO/CO
(Fig.41a). See section 4.0.
12. Complete the relevant section of the "Benchmark"
Installation, Commissioning and Service Record Log
Book and hand it back to the user.
2
ratio at flue sampling point
31