HVDC TRANSFORMER BUSHINGS
Appendix 7 – Bushing installation check list
Bushing type:__________________________________________________________
Bushing Serial Number:__________________________________________________
Substation:____________________________________________________________
Date
Prepared
Item
Description
1
Controls at the arrival
2
Electronic Impact recorder (if installed)
3
Transformer turret treatment data
PHI 530.1425.2500
IS 2664 GB
PHI 265.850.1500
Page 67 of 70
Kepco project
Checked
Activity
Check the wooden crate status.
Check the external visual impact recorder(s).
Open the crate and inspect packaging and goods inside.
Check the pressure of the gas inside the bushing and the gas Dew point.
Check that the oil pressure is ≥1 bar @20° C, record the bushing avg. temperature
Verify the absence of oil leakages from the bushing.
Check the composite insulator status, the top terminal and the relevant accessories.
Check the oil side cone, the contact springs and the relevant accessories
Check the bushing instruments and the status of the electric wiring.
Check the status of the oil valves and the warranty seals
Remove the impact recorder and ship it to GE Energy Connections RPV.
Check that the transformer turret has been processed in accordance with the
Transformer Manufacturer procedure and that oil parameters inside the barriers are in
line with Table 13 data.
Limits / recording
Action on problems
Take pictures and inform GE Energy
No great damages outside.
Connections RPV
Take pictures and inform GE Energy
No intervention of the devices.
Connections RPV
Take pictures and inform GE Energy
No visible damages on goods.
Connections RPV
Check gas pressure:
0.11 MPa abs ≤ Gas pressure ≤0.125 MPa abs
Contact GE Energy Connections RPV
(0.1 bar gauge ≤ Gas pressure ≤0.25 bar gauge)
Dew point ≥-30° C at atmospheric pressure
Pressure and temperature recording
In case of pressure not in line wth the
diagram pressure / temperature
At oil gauge:
_________ bar gauge
evidence of oil leakages contact GE Energy
t
:
_________ ° C
avg
Connections RPV
Take pictures and inform GE Energy
No damages.
Connections RPV
No scratches
Contact GE Energy Connections RPV
No damages
No damages.
Contact GE Energy Connections RPV.
Only for bushings shipped with the electronic
impact recorder
Oil final characteristics:
Water content by KF at 20° C: ________ ppm
If parameters are not OK stop bushing
Breakdown voltage on 2.5 mm gap: ___ kV
installation activities and proceed with a new
Total gas content: _________________ ppm
treatment of the transformer turret.
Power factor at 90° C: ______________
Resistivity at 30° C: ________________ Ω x m
Inform GE Energy Connections RPV.
Particle content ISO class: __________
Date
Signature
Figure 8