Summary of Contents for Backyard Products Yardline BELLINGHAM GABLE 10' x 16'
Page 1
16827 STOP! STOP! Call Us First! DO NOT RETURN TO STORE. For immediate help with assembly or product information call our toll free number: 1-800-844-9273 or email: customerservice@yardline.net Our staff is ready to provide assistance April through October M-F 8:00 AM to 4:30 PM EST Saturday 8:30 AM to 4:30 PM EST November through March M - F 8:00 AM to 5:00 PM EST...
16827 02/08/2016 A Backyard Products Company BELLINGHAM GABLE 10' x 16' (305 x 488 cm) ACTUAL FLOOR SIZE IS 120 x 192" (304,8 x 487,7 cm) KEEP THIS MANUAL FOR FUTURE REFERENCE OPTIONAL: OPTIONAL: OPTIONAL: DOOR LOCATED DOOR LOCATED DOOR LOCATED...
Page 4
TOOLS Required Optional Phillips Tool Belt/ Utility Knife Screwdriver Nail Pouch Shingle Blades Drill / Driver Caulk Gun 1/8" Drill Bit Tin Snips 1/4" Drill Bit (for drip edge) 5/16" Drill Bit Paint Tools 1/2" Drill Bit Chalk Line #2 Philips Drive Bit Safety Glasses Hammer Nail Gun...
ADDITIONAL MATERIALS FOUNDATION OR FLOOR MATERIALS • This shed does not include any floor or leveling materials. • See the FLOOR LEVELING section on page 7 for recommended methods and suggested materials to properly level your floor, as this will vary depending on your specific site. WOOD FLOOR FRAME MATERIAL REQUIRED: Use only wood treated for ground contact and fasteners approved for use with treated wood.
PARTS IDENTIFICATION AND SIZES Part identification WOOD SIZE CONVERSION CHART letters are stamped on some parts. Treated lumber is stamped: Nominal Board Size Actual Size 2" x 4"....1-1/2" x 3-1/2" (3,8 x 8,9 cm) 1" x 4"....3/4" x 3-1/2" (1,9 x 8,9 cm) 2"...
Page 7
PARTS LIST continued... 2 x 3 x10-1/8" (5,1 x 7,6 x 25,7 cm) 2 x 4 x 24" (5,1 x 10,2 x 61 cm) 1 x 4 x 23-7/8" (2,5 x 10,2 x 60,6 cm) 1 x 4 x 96" (2,5 x 10,2 x 243,8 cm) 2 x 4 x 96"...
FASTENERS & HARDWARE NAIL BOXES (not included) 3" (7,6 cm) BOXES 2" (5,1 cm) BOXES FASTENER/ HARDWARE BAG 1-1/2" (3,8 cm) x280 2" (5,1 cm) x152 3" (7,6 cm) 2" (5,0 cm) 1-5/8" (4,1 cm) (NOT ACTUAL SIZE) 3/8" x5-1/2" (1 cm x 14 cm) 3/4"...
Page 9
FLOOR LEVELING OPTIONS There are multiple ways to level your floor frame. Our recommended leveling method is shown below. Leveling materials are not included in this kit. PREFERRED METHOD - 4x4 TREATED RUNNERS • 3" Screws angled into 4x4. • (2) at each point frame •...
Page 10
CONCRETE FOUNDATION Your kit contains all materials to construct a wooden floor. If you choose to install your kit on a concrete slab refer to the diagram below. Treated Sill Plate Caulk between sill plate and concrete. 3-1/2" (8,9 cm) 4"...
FLOOR FRAME PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 117" (5,1 x 10,2 x 297,2 cm) Look for TREATED Stamp 2 x 4 x 192" (5,1 x 10,2 x 487,7 cm) BEGIN Orient parts as shown on fl at surface. Measure and mark. HINT: Use two 3"...
Page 12
LEVEL AND SQUARE FLOOR FRAME Before attaching fl oor decking, it is important to level and square the fl oor frame. A level and square fl oor frame is required to correctly construct your shed. BEGIN See page 7 for the preferred fl oor leveling method. Use level and check the frame is level before applying fl oor panels.
Page 13
FLOOR PANELS PARTS REQUIRED: 2" (5,1 cm) 5/8 x 48 x 96" (1,6 x 121,9 x 243,8 cm) Ensure your floor frame is square by installing one panel and squaring frame. BEGIN Attach the 48 x 96" panel with the rough side up (painted-grid lines side) with the 48" edge and corner flush to the floor frame (Fig A).
Page 14
FLOOR PANELS PARTS REQUIRED: x238 2" (5,1 cm) 5/8 x 48 x 96" 5/8 x 47-7/8 x 48" 5/8 x 23-7/8 x 96" (1,6 x 122 x 243,8 cm) (1,6 x 121,9 x 122 cm) (1,6 x 60,6 x 243,8 cm) Continue installing panels with rough side up (painted grid lines).
Page 15
IMPORTANT! Check the floor frame is level after installing floor panels. Re-level if needed. • The floor should be used as a stable work surface for wall construction. • Organize your assembly procedure during the build process HINT: to avoid over-handling of the walls. GABLE END WALL EAVE SIDE WALL...
RAFTER ASSEMBLY PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 5-7/8" (5,1 x 10,2 x 14,9 cm) It is very important to assemble your rafters using the following method for an even and fl at roof. You will build a rafter jig using the fl oor and three PVA parts as shown. ¸...
Page 17
RAFTER ASSEMBLY PARTS REQUIRED: x 14 x 168 2" (5,1 cm) 1-5/8" (4,1 cm) OSB OR WOOD GRAIN 6 x 24" (15,2 x 61 cm) 2 x 4 x 75-1/4" (5,1 x 10,2 x 191,1 cm) ¸ BEGIN Place two rafters ECN into the jig as shown. Keep ECN fi rm against outside PVA's as shown (Fig.A) and push rafters tight to the middle PVA.
Page 18
STOP CHOOSE YOUR DOOR LOCATION AT THIS TIME AS YOU WILL ASSEMBLE YOUR DOOR WALL FIRST. NOTE: Install doors at opposite side of loft & shelf. GABLE END WALL WITH DOOR: IF YOU CHOOSE THE GABLE END WALL FOR DOOR LOCATION GO TO Next Page TO BEGIN BUILDING YOUR WALLS OPTIONAL:...
Page 19
GABLE END WALL WITH DOOR PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 8-1/2" (5,1 x 10,2 x 21,6 cm) 2 x 4 x 80" (5,1 x 10,2 x 203,2 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) 2 x 4 x 32-1/2"...
Page 20
GABLE END WALL WITH DOOR PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 68-1/2" (5 x 10,2 x 174 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) HINT: Orient parts on edge. Use two 3" nails at each location. For easier nailing stand on frame.
Page 21
GABLE END WALL WITH DOOR PARTS REQUIRED: 2" (5,1 cm) 48 x 84" (121,9 x 213,4 cm) x1 LEFT + 1 RIGHT Place left 48" x 84" panel onto wall frame flush to top of SZ with primed side up as shown. Secure panel with two 2" nails 6" (15,2 cm) apart. Repeat Step 4 to attach the right 48"...
Page 22
GABLE END WALL WITH DOOR PARTS REQUIRED: 2" (5,1 cm) 11-7/8 x 84" (30,2 x 213,4 cm) Place left 11-7/8" x 84" panel onto wall frame fl ush to top of SZ with primed side up as shown. Secure panel with two 2" nails 6" (15,2 cm) apart. Repeat Step 4 to attach the right 11-7/8"...
Page 23
EAVE SIDE WALL WITH DOOR RIGHT PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 8-1/2" (5,1 x 10,2 x 21,6 cm) 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) 2 x 4 x 80"...
Page 24
EAVE SIDE WALL WITH DOOR RIGHT PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 68-1/2" (5 x 10,2 x 174 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) HINT: For easier nailing stand on frame. Orient parts on edge on floor as shown.
Page 25
EAVE SIDE WALL WITH DOOR RIGHT PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE 48 x 84" BLOCK (121,9 x 213,4 cm) Ensure your wall frame is square by installing one panel and squaring frame. Place 48 x 84" panel onto wall frame flush to top of frame with primed side up as shown. Use the gauge block to mark the 3/4"...
Page 26
EAVE SIDE WALL WITH DOOR RIGHT PARTS REQUIRED: x130 2" (5,1 cm) 48 x 84" 48 x 84" 48 x 84" (121,9 x 213,4 cm) (121,9 x 213,4 cm) (121,9 x 213,4 cm) x1 LEFT 1 RIGHT Place 48" x 84" panel on frame as shown with primed side facing up.
Page 27
EAVE SIDE WALL WITH DOOR CENTERED PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 8-1/2" (5,1 x 10,2 x 21,6 cm) 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) 2 x 4 x 80"...
Page 28
EAVE SIDE WALL WITH DOOR CENTERED PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 68-1/2" (5 x 10,2 x 174 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) HINT: For easier nailing stand on frame. Orient parts on edge on floor as shown.
Page 29
EAVE SIDE WALL WITH DOOR CENTERED PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE 48 x 84" BLOCK (121,9 x 213,4 cm) Ensure your wall frame is square by installing one panel and squaring frame. Place 48 x 84" panel onto wall frame flush to top of frame with primed side up as shown. Use the gauge block to mark the 3/4"...
Page 30
EAVE SIDE WALL WITH DOOR CENTERED PARTS REQUIRED: x130 2" (5,1 cm) 48 x 84" 48 x 84" 48 x 84" (121,9 x 213,4 cm) (121,9 x 213,4 cm) (121,9 x 213,4 cm) x1 LEFT 1 RIGHT Place 48" x 84" left door panel on frame as shown with primed side facing up. Nail using 2"...
Page 31
EAVE SIDE WALL WITH DOOR LEFT PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 8-1/2" (5,1 x 10,2 x 21,6 cm) 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) 2 x 4 x 80"...
Page 32
EAVE SIDE WALL WITH DOOR LEFT PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 68-1/2" (5 x 10,2 x 174 cm) 2 x 4 x 67" (5,1 x 10,2 x 170,2 cm) HINT: For easier nailing stand on frame. Orient parts on edge on floor as shown.
Page 33
EAVE SIDE WALL WITH DOOR LEFT PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE 48 x 84" BLOCK (121,9 x 213,4 cm) Ensure your wall frame is square by installing one panel and squaring frame. Place 48 x 84" panel onto wall frame flush to top of frame with primed side up as shown. Use the gauge block to mark the 3/4"...
Page 34
EAVE SIDE WALL WITH DOOR LEFT PARTS REQUIRED: x130 2" (5,1 cm) 48 x 84" 48 x 84" 48 x 84" (121,9 x 213,4 cm) (121,9 x 213,4 cm) (121,9 x 213,4 cm) x1 LEFT 1 RIGHT Place 48" x 84" panel on frame as For squareness maintain fl ush and 3/4"...
Page 35
EAVE SIDE WALL - NO DOOR PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 48" (5,1 x 10,2 x 121,9 cm) 2 x 4 x 80" (5,1 x 10,2 x 203,2 cm) 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) IF YOUR DOOR IS ON THE GABLE SIDE YOU WILL BUILD IDENTICAL WALLS.
Page 36
EAVE SIDE WALL - NO DOOR PARTS REQUIRED: 2" (5,1 cm) 2" (5,1 cm) 3/4" GAUGE 48 x 84" BLOCK (121,9 x 213,4 cm) Ensure your wall frame is square by installing one panel and squaring frame. Place 48 x 84" panel onto wall frame flush to top of frame with primed side up as shown. Use the gauge block to mark the 3/4"...
Page 37
EAVE SIDE WALL - NO DOOR PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE BLOCK 48 x 84" (121,9 x 213,4 cm) Place 2nd 48" x 84" panel on frame as shown with primed side facing up. Nail using 2" nails 6" apart on edges and 12" apart inside panel. For squareness maintain fl ush and 3/4"...
Page 38
GABLE END WALL -A- PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 80" (5 x 10,2 x 203,2 cm) 2 x 4 x 68-1/2" (5,1 x 10,2 x 174 cm) 2 x 4 x 44-1/2" (5,1 x 10,2 x 113 cm) IF YOU CHOSE THE GABLE END WALL FOR DOOR LOCATION ASSEMBLE ONLY GABLE END WALL.
Page 39
GABLE END WALL -A- PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE 48 x 84" BLOCK (122 x 213,4 cm) Place 48" x 84" panel with primed side up onto frame flush at top and with a 3/4" gap on right side. Maintain 3/4"...
Page 40
GABLE END WALL -A- PARTS REQUIRED: 2" (5,1 cm) 23-7/8 x 84" 48 x 84" (60,6 x 213,4 cm) (122 x 213,4 cm) Place 23-7/8" x 84" primed side up and fl ush with installed 48" x 84" panel edge. Ensure panel is fl ush at top.
Page 41
GABLE END WALL -B- PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 80" (5,1 x 10,2 x 203,2 cm) 2 x 4 x 32-1/2" (5,1 x 10,2 x 82,5 cm) 2 x 4 x 80-1/2" (5,1 x 10,2 x 204,5 cm) IF YOU CHOSE THE GABLE END WALL FOR DOOR LOCATION GO TO PAGE 42 STOP HERE.
Page 42
GABLE END WALL -B- PARTS REQUIRED: 2" (5,1 cm) 3/4" GAUGE 48 x 84" BLOCK (122 x 213,4 cm) Place 48" x 84" panel with primed side up onto frame flush at top and with a 3/4" gap on right side. Maintain 3/4"...
Page 43
GABLE END WALL -B- PARTS REQUIRED: x116 2" (5,1 cm) 48 x 84" 11-7/8 x 84" (122 x 213,4 cm) (30,2 x 213,4 cm) For squareness maintain fl ush along panel edges. Flush Place 48" x 84" panel primed side up and fl ush with installed 48"...
Page 44
RIGHT EAVE WALL INSTALLATION PARTS REQUIRED (TEMPORARY): 3" (7,6 cm) 1-1/2 x 2-1/2 x 69" (3,8 x 6,3 x 175,3 cm) 3" (7,6 cm) 2" (5,1 cm) BEGIN Stand right sidewall on fl oor. Center right sidewall assembly on the 192" (487,7 cm) fl oor dimension. Use OO as a temporary brace.
Page 45
GABLE END WALL INSTALLATION PARTS REQUIRED: 3" (7,6 cm) 1-1/2" (3,8 cm) 2" (5,1 cm) 3" (7,6 cm) 2" (5,1 cm) BEGIN 2" (3,8 cm) Flush Screw Flush Stand gable end wall on fl oor. STEP FIRST It is important to secure the gable end wall SCREW Fig.
Page 46
LEFT EAVE WALL INSTALLATION PARTS REQUIRED: 3" (7,6 cm) 1-1/2 x 2-1/2 x 69" (3,8 x 6,3 x 175,3 cm) 2" (5,1 cm) 1-1/2" (3,8 cm) 2" (5,1 cm) BEGIN Stand left sidewall on floor. Center EAVE WALL assembly on the 144" (365,8 cm) Panel Flush floor dimension.
Page 47
LEFT EAVE WALL INSTALLATION PARTS REQUIRED: x12 -or- x16 3" (7,6 cm) x22 -or- x32 2" (5,1 cm) Nail lower edge of panels to fl oor frame using 2" nails 6" apart. Angle nail to hit fl oor frame (Fig. D). Secure eave wall bottom plates to fl oor using 3"...
Page 48
GABLE DOOR WALL INSTALLATION PARTS REQUIRED: 3" (7,6 cm) 2" (5,1 cm) 2" (5,1 cm) 3" (7,6 cm) 1-1/2" (3,8 cm) BEGIN Remove Temporary Supports and stand gable door wall on floor. It is important to secure the front wall in the following order: Set second gable wall on floor and secure using one 2"...
Page 49
GABLE DOOR WALL INSTALLATION PARTS REQUIRED: Nail lower edge of panels to fl oor using 2" nails 6" apart. Angle nail to hit fl oor frame (Fig. C). 2" (5,1 cm) Nails 6" (15,2 cm) Angle nail to hit fl oor frame.
Page 50
GABLE PANELS PARTS REQUIRED: 1-1/2" (3,8 cm) 2 x 4 x 24" (5,1 x 10,2 x 61 cm) 2 x 3 x 75-1/4" (5,1 x 7,6 x 191,1 cm) TEMPORARY SUPPORT BEGIN You will build TWO assemblies. Orient RL and ECA on fl at as shown. Place LEFT front gable panel as shown and secure using 1-1/2"...
Page 51
GABLE LADDERS PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 4-7/8" (5,1 x 10,2 x 12,4 cm) 2 x 3 x 75-1/4" (5,1 x 7,6 x 191,1 cm) BEGIN Orient parts as shown (Fig. A). You will build FOUR assemblies (Fig. B). Arrange, measure and mark locations of four CLA as shown place ECA on top.
Page 52
GABLE ASSEMBLIES PARTS REQUIRED: 3" (7,6 cm) 1-5/8" (4,1 cm) 2 x 4 x 5-7/8" x2 Gable Assemblies x2 Ladder Assemblies (5,1 x 10,2 x 14,9 cm) Orient gable and ladder assemblies as shown (Fig. E). You will build TWO complete assemblies. Ensure gable panels are fl ush at peak of ladder and fl ush along top edge of ladder assembly.
Page 53
GABLE UNITS PARTS REQUIRED: 3" (7,6 cm) 2" (5,1 cm) x2 Gable Units BEGIN Attach gable unit on front wall top plate. It is important to secure the gable unit in the following order: Measure 1-1/2" down from top plate and mark at each side as shown. Set gable unit on top plate. Hold secure with one 2"...
Page 54
RAFTERS PARTS REQUIRED: 3" (7,6 cm) Preassembled Rafter ¸ BEGIN Locate fi rst rafter on top plate. Align rafter over studs at each side and tight to side wall (Fig. A, Fig B). Rest notch on top plate. Secure rafter to top plate with one 3" screw from under top plate (Fig. B, C). Continue securing rafter to top plate with two 3"...
Page 55
RAFTERS PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 5-7/8" (5,1 x 10,2 x 14,9 cm) 2 x 3 x 22-1/2" (5,1 x 7,6 x 57,1 cm) BEGIN Place eave nailer LV between 4th and 5th rafters from LEFT gable wall as shown. Keep LV fl ush to bottom of outside edge of rafter (Fig.
Page 56
ROOF PANELS PARTS REQUIRED: x246 2" (5,1 cm) 3/4" GAUGE BLOCK 7/16 x 27-1/4 x 80-5/8" 27-1/4" x 48" (69,2 x 204,8 cm) (69,2 x 121,9 cm) Roof panels may cause serious injury until securely fastened. BEGIN Attach the 27-1/4" x 80-5/8" panel with the rough side up (painted-grid lines side) with a 3/4" (1,9 cm) measurement on the rafter (Fig A) and the panel flush at the gable end overhang (Fig.
Page 57
ROOF PANELS PARTS REQUIRED: Attach another 80-5/8" x 32-5/8" roof panel, rough side up, flush with the installed 27-1/4" x 48" panel (Fig. C) and flush with the rafter ends (Fig. B). Secure panel with two 2" (5,1 cm) nails in the corners. Two Nails Flush Fig.
Page 58
ROOF PANELS PARTS REQUIRED: 48" x 96" 48" x 31-7/8" 48" x 47-7/8" (121,9 x 243,8 cm) (121,9 x 81 cm) (121,9 x 121,6 cm) Place a 48" x 31-7/8" upper roof panel with the rough side up and flush to lower panels. Ensure 5/8"...
Page 59
ROOF PANELS 3/4" Place a 48" x 47-7/8" upper roof (1,9 cm) panel, rough side up and fl ush MAINTAIN RAFTER TO with the installed panels (Fig.C). RAFTER DIMENSION Gauge Block Ensure 3/4" measurement on the rafter (Fig. A). Secure the lower edge of roof Fig.
Page 60
GABLE END SOFFITS PARTS REQUIRED: 2" (5,1 cm) 3/8 x 7-7/8 x 73-5/16" (1 x 20 x 186,2 cm) Ensure soffi t boards are fl ush at seam (Fig. B) and fl ush at peak (Fig. D). BEGIN Position right 73-5/16" overhang board Primed Side Down fl ush to front wall (Fig A) and gable panel seam (Fig B).
Page 61
EAVE SIDE SOFFITS PARTS REQUIRED: 2" (5,1 cm) 3/8 x 5-7/8 x25-1/2" (1 x 14,9 x 64,8 cm) 3/8 x 5-7/8 x 72" (1 x 14,9 x 182,9 cm) 3/8 x 5-7/8 x 96" (1 x 14,9 x 243,8 cm) Ensure soffi...
Page 62
GABLE FASCIA PARTS REQUIRED: 2" (5,1 cm) Painted Red 3/8 x 4-3/4 x 75-7/8" (1 x 12,1 x 192,7 cm) Painted Green 3/8 x 4-3/4 x 75-7/8" (1 x 12,1 x 192,7 cm) BEGIN Position fascia with primed side out and fl ush to peak and roof panels as shown (Fig. A, Fig B). Secure using 2"...
Page 63
EAVE SIDE FASCIA PARTS REQUIRED: 2" (5,1 cm) 3/8 x 4-3/4 x 32-5/8" (1 x 12,1 x 92,9 cm) 3/8 x 4-3/4 x 80-5/8" (1 x 12,1 x 204,8 cm) 3/8 x 4-3/4 x 96" (1 x 12,1 x 243,8 cm) BEGIN Position 4-3/4"...
Page 64
DOORS PARTS REQUIRED: 3/4" (1,9 cm) 15235 10-1/2 x 32-1/2" (26,7 x 82,6 cm) Left Door Right Door ¸ BEGIN Lay doors face down on a clean flat surface. Apply high quality exterior-grade caulk behind frame near edge before installing to seal window. From back side of door, position window in opening and ensure square with door edge.
Page 65
DOORS PARTS REQUIRED: 3" (7,6 cm) 1-1/2 x 2-1/2 x 69" (3,8 x 6,3 x 175,3 cm) 1-5/8" (4,1 cm) 1 x 3 x 5" (2,5 x 7,6 x 12,7 cm) Left Door Assembled Right Door Assembled Orient parts as shown on flat surface. 3/8"...
Page 66
DOORS PARTS REQUIRED: 3" (7,6 cm) 1-1/2 x 2-1/2 x 69" (3,8 x 6,3 x 175,3 cm) Attach temporary support OO as a ledger board fl ush under wall panels for doors to rest on, using three 3" screws (Fig. A) . Carefully cut bottom wall frame 2 x 4 fl ush with door frame using a saw (Fig.
Page 67
DOOR PARTS REQUIRED: 3/4" (1,9 cm) x11 2" (5,1 cm) Bagged seperately / special coating 19/32 x 3 x 26-5/8" (1,5 x 7,6 x 67,6 cm) 64" Metal Threshold 3/4" (1,9 cm) 19/32 x 3 x 72" (1,5 x 7,6 x 183 cm) BEGIN Secure door trim from inside using 3/4"...
Page 68
DOOR STIFFENERS PARTS REQUIRED: 2" (5,1 cm) 1-1/2 x 2-1/2 x 69" (3,8 x 6,3 x 175,3 cm) BEGIN Center OO vertically on the left door in the door opening fl ush with the edge of door (Fig. A). Secure using (7) 2" screws through outside trim into OO (Fig. B) Repeat Steps 1-2 to install OO on right door.
DOOR HARDWARE PARTS REQUIRED: 1/2" (13 mm) Drill Bit 1/4" (6 mm) Drill Bit 3/4" (1,9 cm) BEGIN Measure and mark location of hole on outside of right door as shown (Fig. A) . Pre-drill hole with 1/4" drill. Re-drill hole with 1/2" drill (Fig. B) . Keep drilled hole square to trim to avoid breaking edge of 1-1/2"...
DOOR HARDWARE PARTS REQUIRED: 3-Point Door Locking Mechanism Handle (locking) with Screws 1-1/4” x2 3/4” Tech Screw with drill point 1-1/4” x8 1/2" (13 mm) Drill Bit 1-1/4” x2 1/4" (6 mm) Drill Bit Secure backplate with 1" screws and handle with 1-1/4" screws as shown. RIGHT DOOR Backplate Screw...
Page 71
DOOR HARDWARE See following pages for mounting locations of brackets and plates. Plate Washer 1-1/4" Pan Head Screw UPPER BRACKET 3/4" Tech (with offset) Screw Orient bracket as shown. Washer 3/4" Tech Screw Washer LOWER BRACKET (with offset) Orient bracket as shown. 1-1/4"...
Page 72
DOOR HARDWARE TOP of Door 2-1/4" IMPORTANT! This rod to edge of door RIGHT DOOR LEFT DOOR Make sure rods are straight up and down when locating brackets. 2-1/4" BOTTOM of Door...
Page 73
DOOR HARDWARE Drill with 3/8" bit PLATE to 2" depth. FRAMING Align Plates with vertical rod points. Drill-thru with 3/8" drill bit to 2" depth into header and floor. VERTICAL RODS FLOOR PLATE...
Page 74
CORNER TRIM PARTS REQUIRED: 2" (5,1 cm) 3/8 x 1-3/4 x 82-1/2" (1 x 4,4 x 209,6 cm) 3/8 x 1-3/4 x 81-7/8" (1 x 4,4 x 208 cm) ¸ BEGIN Attach one 81-7/8" trim board fl ush under soffi t panel and against eave wall (Fig. A, B) using one 2"...
Page 75
SHELF PARTS REQUIRED: 2" (5,1 cm) 3/8 x 8 x 12-1/2" (1 x 20,3 x 31,8 cm) 2 x 3 x10-1/8" (5,1 x 7,6 x 25,7 cm) NOTE: Install the shelf and loft on the gable wall farthest from the door location. Always install the shelf and loft on wall with six (6) studs.
Page 76
SHELVING PARTS REQUIRED: 2" (5,1 cm) 7/16 x 11-7/8 x 96" (1,1 x 30,2 x 243,8 cm) 7/16 x 11-7/8 x 23-7/8" (1,1 x 30,2 x 60,6 cm) 1 x 4 x 96" (2,5 x 10,2 x 243,8 cm) 1 x 4 x 23-7/8" (2,5 x 10,2 x 60,6 cm) Install shelf panels centered over shelf supports.
Page 77
LOFT PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 24" (5,1 x 10,2 x 61 cm) 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) NOTE: Install the shelf and loft on the gable wall farthest from the door location. Always install the shelf and loft on wall with six (6) studs.
Page 78
LOFT PARTS REQUIRED: 3" (7,6 cm) 2 x 4 x 24" (5,1 x 10,2 x 61 cm) (NOT ACTUAL SIZE) 3/8" x5-1/2" (1 cm x 14 cm) 2 x 4 x 96" (5,1 x 10,2 x 243,8 cm) Hex Bolt 3/8"...
Page 79
LOFT PARTS REQUIRED: 2" (5,1 cm) 48" x 96" (112,4 x 243,8cm) Install loft panel centered over loft joists. Secure with 2" (5,1 cm) nails 8" (20,3 cm) apart. There will be a gap of approximately 8-1/2" on either side. 8 "...
Page 80
STOP CHOOSE YOUR EAVE WALL WINDOW LOCATIONS AT THIS TIME. WINDOW LOCATION EXAMPLES EAVE WALL WINDOW FRAMING PARTS REQUIRED: 3" (7,6 cm) Window Kit See instructions packaged in your Window Kit for window and trim installation. BEGIN From inside, measure and mark locations of window framing 2x3's (included in window kit). Window framing 2x3's must be installed flush to panel and square with studs.
Page 81
EAVE WALL WINDOW CUTOUT PARTS REQUIRED: 3/8" (1,0 cm) Drill Bit Working from inside use a 3/8" drill bit to drill a hole through wall panel in each corner of window framing. Pre-drill hole 3/8" (1.0 cm) From outside, mark straight lines connecting the holes. Cut along lines using a saw.
Page 82
COLLAR TIES PARTS REQUIRED: 2" (5,1 cm) 1 x 3 x 72" (2,5 x 7,6 x 182,9 cm) BEGIN Position and level collar tie HJ on fourth rafter from loft side of shed. HINT: For best appearance install collar tie on rafter facing away from door opening. Attach with 2"...
Page 83
GABLE VENTS PARTS REQUIRED: #8 x 1" (2,5 cm) Pan Head Screws #15021 ¸ BEGIN Locate vent in the gable wall as shown. Secure using 1" (2,5 cm) screws. Repeat STEPS 1 - 2 to install vent on the opposite gable wall. #8 x 1"...
Page 84
PAINT & CAULK - NOT INCLUDED - • Use acrylic latex caulk that is paintable. Caulk at all horizontal and vertical seams, between the trim and walls, and all around the door trim. • Use a high quality exterior acrylic latex paint. When painting your building, there are a few key areas that can be easily overlooked that must be painted: •...
Page 85
SHINGLES - NOT INCLUDED - • Follow directions provided by manufacturer and these instructions. Familiarize yourself with a 3-Tab Shingle. Notch Notch SHINGLE NAIL PATTERN 1/2" 1" Sealing Strip 1" (1,3 cm) (2,5 cm) (2,5 cm) Half A Rain Slot Full Rain Slot NAILS NEVER DRIVE FASTENERS INTO OR ABOVE SEALING STRIPS.
Page 86
SHINGLES continued... Beginning at front of shed, install first row of shingles with notch at 1" past roof edge or flush with drip edge. Roof Deck FRONT OF BACK OF SHED SHED 1" (2,5 cm) Flush with starter row. Notch - or - Drip Edge Flush with starter row.
Page 87
SHINGLES continued... Continue installing rows of shingles to the peak. At the peak make sure there is a maximum of 5" or less to the rain slot, as shown below. If shingles overlap at ridge cut to peak with a utility knife. 5"...
Page 88
SHINGLES - RIDGE CAP • You will finish off the top of the roof with a ridge cap made from shingles. BEGIN Cut shingles into THREE pieces. Hint: Use cut-off pieces first. 2" 2" (5 cm) (5 cm 2" 2" 2"...
Page 89
SHINGLES - RIDGE CAP continued... Continue installing ridge cap to back of roof. Make sure there is 4" between the shingle-color and edge of shingles. 4" (10 cm) Trim cap off fl ush to shingles When you have 4" minimum of shingle color cut one piece to cap your roof. Cut at top of rain slot.
Page 90
WARRANTY REGISTRATION Please complete your warranty registration to properly validate your warranty. Register your product online at: www.OnlineWarranty.net LIMITED CONDITIONAL WARRANTY* Backyard Storage Solutions, LLC warrants the following: Every product is warranted from defects in workmanship and manufacturing for 1 year. All accessories, hardware and metal components are warranted for 2 years.