Suggested Method of Installation
1.
Mounting Da-Lift Projector Lift between joists.
Install the joists at the proper height and width to fit the Da-Lift
you are installing. See Figure 1.
NOTE: The Da-Lift must be installed on top of the joists.
Be sure to leave access from above for installation.
When the joists are properly installed, and secured in place, slide
the Da-Lift in position. Bolt the two brackets (38mm x 483mm)
to the frame. Lower the unit onto the joists and secure in place.
Additional bracing may be required, based on construction.
NOTE: Da-Lift projector lift must be installed level!
Lifting
Model
Capacity
Da-Lift 10M
Da-Lift 15M
Da-Lift 15
Da-Lift 19
Da-Lift 19L
2. Mounting Da-Lift Projector Lift using threaded rods.
Secure four threaded rods to the ceiling at the dimensions
shown. See Figure 2, "E" and "F". Install the mounting bracket
(38mm x 483mm) to each side of Da-Lift with 1/2" diameter bolts,
flat washers and nuts. Attach one nut on each rod and run the
nut up to the desired height.
Slide Da-Lift projector lift up with all (4) four threaded rods into
the mounting brackets. Install nuts under the mounting brackets.
Adjust the frame to the proper height and level with bottom nuts
on the rod. Lock the mounting brackets in place with the nuts on
the top of each rod. Frame must be level and solid. Additional
bracing may be required, based on construction.
Width
A
9.0N
575mm
9.0N
575mm
67.4N
781mm
67.4N
832mm
67.4N
1086mm
B
D
Figure 1
Height
Depth
B
C
381mm
559mm
508mm
559mm
508mm
864mm
610mm
965mm
610mm
1219mm
Figure 2
A
Height
Dim.
D
E
114mm
613mm
241mm
613mm
241mm
819mm
343mm
870mm
343mm
1124mm
E
C
Dim.
F
356mm
356mm
413mm
413mm
413mm
F