Electrical Connections; Opening The Maintenance Compartment Door - Huawei SUN2000-55KTL Series Quick Manual

Hide thumbs Also See for SUN2000-55KTL Series:
Table of Contents

Advertisement

4

Electrical Connections

4.1
Installing the Ground Cable
4
The ground point on the enclosure is preferred to connect to the PE cable for the SUN2000.
The ground point in the maintenance compartment is mainly used for connecting to the ground
cable included in the multi-core AC power cable. For details, see section "4.3 Installing AC
Output Power Cables."
You need to prepare M6 OT terminals by yourself.
The outdoor copper-core cable with a cross-sectional area of 16 mm
ground cable must be secured.
It is recommended that PGND cable of the SUN2000 be connected to the nearest ground point.
For a system with multiple SUN2000s connected in parallel, connect the ground points of all
SUN2000s to ensure equipotential connections to ground cables.
To enhance the corrosion resistance of the PE terminal, apply silica gel or paint on it after
connecting the PGND cable.

Opening the Maintenance Compartment Door

4.2
1. Never open the host panel of the SUN2000.
2. Before opening the maintenance compartment door, turn off the downstream AC output switch
and the two DC switches at the bottom.
3. If you need to open the maintenance compartment door on rainy or snowy days, take protective
measures to prevent rain and snow entering the maintenance compartment. If it is impossible to
take protective measures, do not open the maintenance compartment door on rainy or snowy
days.
4. Do not leave unused screws in the maintenance compartment.
1. Loosen the two screws on the maintenance compartment door using a security torx wrench.
6
2
is recommended. The

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-60ktl series

Table of Contents