Load Management Function Setting On Ems Lcd - Alpha ESS EMS Introduction Manual

Table of Contents

Advertisement

Your Smart Energy
If the backup box is used as meter and connected in the whole system, the diagram is
as below:
If the grid fails, the energy storage system will provide power to all loads.

7.1 Load Management Function Setting on EMS LCD

Enter "Setting" page and select "Function". Enter "Function" page and select "Backup
Box". Enter "Backup Box" page and replace "No" to "Yes". Press "Enter" button on EMS
to confirm.
Press "↓" button and enter "Backup Box" setting page to set up Priority and the SOC
to manage your loads.
NOTE: With the highest priority, the SOC must be lowest. You can set the priority
as 1, 2, and 3. If you set L1 as 1, L1 being the highest priority, then the SOC must
be set to the lowest. When the SOC is lower than your setting, the load will be
cut off in the order as you set.
___________________________________________________________________
Alpha ESS Co., Ltd.
Page 15 of 16

Advertisement

Table of Contents
loading

Table of Contents