Pick a suitable location to install the universal lifting device. Ensure to have
sufficient wall clearance for lifting loads. Make sure not to lift loads over
people or animals.
Select a massive wooden beam or a stone or concrete surface as mounting
surface for the frames. The lifting device must not be attached to a thin or
rotten ceiling! Use the included special dowels (10) when attaching the
installation plates to a stone/concrete ceiling. When mounting on other media
use appropriate mounting hardware (screws, dowels, etc. - not included).
When used as a bicycle lift, measure the distance from the end of the bicycle
seat to the handlebars. Attach the two installation plates (8) in that distance at
the desired location on the ceiling.
When used as a kayak lift, a distance of about 1.50 to 2.50 m can be chosen
– depending on the type and length of the kayak to be lifted.
Mount the pull rope fastening (2) with the two mounting screws (3) in an
accessible place (about 1.20 m in height).
Thread the pull rope through the pulleys as follows:
1. Attach the one end of the rope with a knot at the outer bottom hole of the right
frame (6), as shown on figure 1.
2. Then lead the rope through the pulley of the right hook
(9). Make sure that the hook is facing inside.
3. Now lead the rope over the pulley of the right frame (6).
4. Pull the rope to the left frame (7) and lead it over the
pulley and then through one of the guide holes of the
brake mechanism (see figure 2).
5. Now lead the pull rope down and run it around the pull
rope fastening (2) in a loop.
6. Lead the pull rope from the pull rope fastening up
through the other guide hole of the brake mechanism.
7. Lead the rope through the second pulley of the left
frame (7) and run it through the pulley of the left hook
(9). Make sure that the hook is facing inside.
8. Then lead the pull rope through the outer lower hole of
the left installation plate (8) and secure it with a knot.
9. Insert the two frames (6) and (7) into the pre-assembled installation plates (8)
and screw them together using the supplied installation screws and nuts (1).
Operation