Ⅰ STRUCTURE AND FUNCTION This kind of machine is under-drive structure, The small chain wheel which equiped on speed-control motor will take big chain wheel directly, drive the eccentricity wheel of spindle moving seasonally. The mainly part, like machine shelves, upper blade, worktable and so on is steel welding structure.
Ⅲ Transportation and installation Transportation : Keep balance when transport the machine! When you transport the machine with fork truck, please refer to picture 1. Installation: Put each mat down to the four ground holes, the depth into the earth must be over 500mm, please refer to picture 2. The Installation methods is that Please set apart the place for the groud holes when the first concrete pouring, put then the machine on the ground after concreting,...
The second The first concrete concrete pouring pouring Picture 2 Ⅳ Preparation and test drive 1、 The machine must be cleared after assembling. 2、 Avoid any loosing at the joint part of nut and screw. Make sure there is no barriers at the parts for transferring.
Ⅴ Adjustment for the shearing edge gap 1. Relation between Plate thickness with cutting edge data (Picture 3) (Cutting edge data can cut 2mm when the machine was made out) Thickness (mm) 0.05 0.10 0.15 0.20 Cutting edge(mm) Picture 3 2.
Picture 4 Ⅵ Lubrication (Picture 5) ITEM Lubricate place Quantity Lubricate period Lubricating oil Copper Bushing Once every shift Machine oil Shaft of upper blade Once every shift Machine oil frame Back guard screw bar Once every shift Machine oil...
Page 8
Motor direction Picture 5 This machine should be manual lubricated point by point regularly, the safety guard on the two sides should be removed when you lubricate the point 1 and 2 in the picture 5. Viz. the part Nr.52 and Nr.57 in the exploded drawing.
VII Maintenance 1、 The machine should be used by an experienced operator. The operator must read this manual carefully before operating. 2、 Keep work area clean. Paint rust-proof oil on un-painted section and sliding section of the machine. 3、 Keep shearing blade edge sharp. If you find any damage or wear or bull, please re-grind the blade or change a new blade.
Page 13
Parts list: Item Description Specification Remark M8X45 washer Back protective screening plastic Plugging covered Upper protective screening retaining rings for shafts M8X70 column nut washer profile-safety guard Ⅰ cover bolt M8X55 corbel piece square nut adjustable shelves M8X40 bolt M6X12 column nut rubber mat retaining rings for shafts...
Page 14
profile-safety guard Ⅱ washer M6X12 half-column nut upper shield M5X10 half-column nut washer light upper-blade shelves Brake pad M5X8 Cross recessed countersunk head screw Back Slide bar M5X12 socket set screws with taper point Front slide bar safety guard safety guard Sheet holder for springs blade easily damaged parts...
Page 19
Electric shearing Machine OPERATION MANUAL (Electric System) BRIEF INTRODUCTION This operation manual shows you the connection, use and maintenance for interface of electrical system and mechanism, and maintenance of Electric shearing machine. Before operation, please read the manual carefully, to avoid the damage of equipment and body.
Page 20
IV: SETTING and OPERATION After the power, please operate the machine according to following steps: 1, Shearing operation 1). Turn the switch “SA4” to the single stroke position in the left. Step ↑↓ ↓↑↓↑ The motor will be stopped after once on the pedal switch, motor begin to work.
Page 21
C. The foot switch is damaged, you have to replace it. 2. The machine continues working in single stroke state. The position of travel switch SQ2 is changed or damaged, you have to adjust it to the right position or replace it. 3.
Need help?
Do you have a question about the HU 1300 X 4 ES and is the answer not in the manual?
Questions and answers