Open Kettle Gas Fryers 718LCG, 724CG & 734CG Operator’s Manual Belshaw Adamatic Bakery Group. 814 44 Street Northwest, Suite 103 Auburn, WA 98001 USA Phone: (206) 322-5474 • Fax: (206) 322-5425 E-mail: service@belshaw.com • www.belshaw.com...
Page 3
BELSHAW-ADAMATIC FREIGHT To unpack the fryer and transport it to the DAMAGE POLICY workstation: Belshaw-Adamatic has made every effort to Use a fork lift to transport the shipping crate insure that your equipment arrives in good to the work station. condition.
Contents Preface Operation Taking Safety Precautions Filling with Shortening If the Pilot Light Fails to Ignite High Temperature Limit Switch Adding Shortening to the Fryer Fill up to “OIL LEVEL” Marks Cleaning Removing the Shortening Washing Rinsing Donut-Making Helps Tips on Making Quality Cake Donuts Calculating Correct Water Temperature Ratios of Plunger Sizes to Donut Weights Temperature Conversion...
Preface The 718LCG, 724CG, and 734CG Gas Fryers are get spilled on the floor, mop it up designed to fry cake and yeast-raised donut immediately. Materials on the floor can products. Each must be bolted to a flat, dry cause people to slip or fall, resulting in floor.
Operation Taking Safety Precautions * If you have a Belshaw EZMelt shortening melter-filter, warm the In a prominent location, post information about shortening and then transfer it to the what to do if there is a gas leak. Make sure that kettle.
Above: OMRON Digital Temperature Controller (See diagram above) On the digital If this happens, follow these steps to reset the temperature controller, push the up and down system: arrow keys to adjust the target frying temperature a. Move the on/off switch to the OFF (SV).
* If you have a Belshaw EZMelt shortening melter-filter, warm the shortening and then transfer it to the kettle. (For EZMelt operating instructions, refer to the EZMelt operator’s manual) * Melt shortening in a pan on the stove and pour it into the kettle. * Very carefully put solid shortening into the kettle.
Cleaning For your safety, observe the following warnings 1. Disconnect the machine from the power throughout the entire cleaning process. source. 2. Let the shortening cool to 250°F(120°C). WARNING 3. Place a Belshaw EZMelt Filter under the drain valve of the fryer. (See your EZMelt Thoroughly clean and dry the floor if Operator’s Manual) shortening, water, or other materials are...
WARNING WARNING To avoid fire, serious injury, and Do not use plastic containers. If the equipment damage, do not attempt to burn cleaning solution is not cool enough, the carbon off of the heat tubes. containers will melt; possibly causing you to be burned, and causing cleaning solution to get on the floor.
Page 11
CAUTION WARNING To avoid severe damage to the kettle, never Thoroughly clean and dry the floor if water turn on the heat unless the heat tubes are is spilled. Water on the floor can cause completely covered by liquid. serious injury or loss of life. 2.
Donut-Making Helps Tips on Making Quality If the shortening is too cold, the donuts will spread too rapidly, will form large rings, will Cake Donuts tend to crack open, will be too light in appearance, and will absorb too much •...
Calculating Correct Water use your own room temperature, dry mix temperature, desired batter temperature, and, if Temperature you are making yeast-raised donuts, estimated temperature increase during mixing. The following is an example of how to calculate the correct water temperature to use. You must Cake Donuts Yeast-Raised Donuts °F...
Page 14
Open Kettle Gas Fryers 718LCG, 724CG & 734CG Technical Supplement Belshaw Adamatic Bakery Group. 814 44 Street Northwest, Suite 103 Auburn, WA 98001 USA Phone: (206) 322-5474 • Fax: (206) 322-5425 E-mail: service@belshaw.com • http://www.belshaw.com...
Page 15
Table of Contents Preface Installation Conforming to Codes Selecting a Workstation Unpacking the Fryer Initial Cleaning Assembling the Fryer Installing the Fryer Moving the Fryer Mounting the Drain Tray Assembling the Frying Screen Handles ...
Preface The 718LCG, 724CG, and 734CG Gas Fryers are get spilled on the floor, mop it up designed to fry cake and yeast-raised donut immediately. Materials on the floor can products. Each must be bolted to a flat, dry cause people to slip or fall, resulting in floor.
Installation In a prominent location, post instructions to be pressure testing of the gas supply piping followed in the event the user smells gas. Obtain system at test pressures equal to or less than this information by consulting your local gas 13.0 IWC (3.45 kPa).
The workstation should allow at least 2”/5 cm a. Slide the flange on the bottom of the flue clearance between the machine and all stack underneath the retaining strip on construction, whether combustible or the flue base. The mounting holes must noncombustible.
holes in the heat shield and the fryer cabinet b. If the fryer is not level, lift the fryer must line up. See Figure 1-2. using a fork lift or pallet jack, and turn the legs to adjust them. c. Using the fork lift or pallet jack, lower the fryer to the floor.
must use a compound that resists the Allow the machine and the shortening to action of liquefied petroleum (LP) gases. cool. d. Bleed the gas lines of all air. WARNING e. Check all gas connections and fittings for leaks using a gas leak detector, a Do not touch hot shortening.
Mounting the Drain Tray 7. Slide the drain tray hinge shaft through the The drain tray is mounted on the right side of the holes in the mounting brackets and the drain fryer in the factory. To move the drain tray on tray.
Assembling the Frying Screen Handles (Be aware that you may be using detachable handles rather than fixed handles, particularly when making raised donuts using screens which are placed inside a proofer. In this case, your handles should NOT be attached to screens.) Frying Screens come with handles and hardware unassembled.
Maintenance Open Kettle Temperature Controller Programming procedure (Service Bulletin SB-0439-R3) This service bulletin covers the proper procedure for programing the Omron E5CC-RX3DM-000 temperature controller in an open kettle fryer. The Belshaw part number is TJ-0184C-2. This controller is programmed and protected so the operator cannot change the setup parameters. You must first unlock the controller to adjust the settings.
Page 24
SB-0439 R3 02/06/15 Century and Open kettle fryer Temperature Controller Programming procedure This service bulletin covers the procedure for programing the TJ-0184C-2 (Omron E5CC-RX3DM-000) temperature controller used on Century and Open kettle fryers. The TJ-0184C-2 controller comes per-programmed and protected so the operator cannot change the setup parameters. To change any setting you must first unlock the controller.
Page 25
SB-0439 R3 02/06/15 To change operator level parameters: (Must be unlocked) 1. Press the O key for less than 1 second 2. Press the M key to move to the next parameter 3. Press the U or D to change the parameter 4.
Page 26
SB-0439 R3 02/06/15 To change advanced level parameters: (Must be unlocked) 1. Unlock the controller 2. Press the O key for more than 1 second to adjust intial parameters 3. Press the M key until you get to parameter amov 4.
Troubleshooting If you have a problem with your fryer that you CAUTION cannot solve, call your dealer or another qualified technician. If you perform repairs yourself or have If your dealer cannot help you, please call them performed by anyone other than a Belshaw Bros.
Step 1: Perform Visual Inspection about the Honeywell S8600 Intermittent Pilot Make sure the fryer’s on/off switch is in the Module. The Belshaw 718LCG, 724CG, and OFF position. Make sure all wiring 734CG gas fryers all use this module. Fryers connections are clean and tight.
to spark as long as the fryer’s thermostat calls for Compare this time with the shutoff time that heat or until the pilot lights. is stamped on the module. They should be the same. The S8600H, which is used on propane fryers, provides 100 percent shutoff and safety lockout.
Page 30
START Thermostat calls for heat. TRIAL FOR First main valve opens. IGNITION Gas flows to pilot burner. Igniter-sensor sparks. Pilot burner lights. Pilot burne r does not light, or Module sense s flame current. mod ule d oes not sense flame current. Module S8600H Module S8600 F System locks out.
Step 5: Check Normal Operation models must be reset by setting the thermostat below 200°F/93°C for at least 1. Move the on/off switch to ON. one minute before continuing. On retry Set the temperature controller to 200°F models, wait for retry or reset at the (93°C) or higher.
Page 32
A common ground, usually supplied by the pilot Check the table below. burner bracket, is required for the module and the pilot burner/igniter-sensor. Check for good metal-to-metal contact between the pilot burner bracket and the Arc Length What To Do main burner.
Page 33
short to ground. Replace the igniter- sensor if necessary. Appearance Cause e. At the gas control, disconnect the main valve wire from the TH or MV terminal. small blue flame lack of gas due to clogged orifice filter f. Connect the fryer to the power source and move the on/off switch to the ON lack of gas due to position.
Page 34
Go To Pages Listed Below MARK FOR YOUR NAT GAS/ FINAL MANIFOLD FRYER ITEM NUMBER MODEL VOLTS PROPANE ASSEMBLY PIPING ELECTRICAL 21263-10 14-15 20-27 718LCG 120V 21264-10 14-15 20-27 718LCG 120V 21268-10 14-15 28-35 718LCG 208-240V 21267-10 14-15 28-35...
Page 53
724G-1718_CV FOR 120V GAS FRYERS PAGE 1 OF 4 MODEL: 718LCG ITEM NUMBERS: 21263-10, 21264-10 MODEL: 724CG ITEM NUMBERS: 21273-10, 21281-10 MODEL: 734CG ITEM NUMBERS: 21276-10, 21277-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 55
724G-1718_CV FOR 120V GAS FRYERS PAGE 2 OF 4 MODEL: 718LCG ITEM NUMBERS: 21263-10, 21264-10 MODEL: 724CG ITEM NUMBERS: 21273-10, 21281-10 MODEL: 734CG ITEM NUMBERS: 21276-10, 21277-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 57
724G-1718_CV FOR 120V GAS FRYERS PAGE 3 OF 4 MODEL: 718LCG ITEM NUMBERS: 21263-10, 21264-10 MODEL: 724CG ITEM NUMBERS: 21273-10, 21281-10 MODEL: 734CG ITEM NUMBERS: 21276-10, 21277-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 59
724G-1718_CV FOR 120V GAS FRYERS PAGE 3 OF 4 MODEL: 718LCG ITEM NUMBERS: 21263-10, 21264-10 MODEL: 724CG ITEM NUMBERS: 21273-10, 21281-10 MODEL: 734CG ITEM NUMBERS: 21276-10, 21277-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 61
724G-1719_CV PAGE 1 OF 4 FOR 208-240V GAS FRYERS MODEL: 718LCG ITEM NUMBERS: 21267-10, 21268-10 MODEL: 724CG ITEM NUMBERS: 21282-10, 21287-10 MODEL: 734CG ITEM NUMBERS: 21278-10, 21280-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 63
724G-1719_CV PAGE 2 OF 4 FOR 208-240V GAS FRYERS MODEL: 718LCG ITEM NUMBERS: 21267-10, 21268-10 MODEL: 724CG ITEM NUMBERS: 21282-10, 21287-10 MODEL: 734CG ITEM NUMBERS: 21278-10, 21280-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 65
724G-1719_CV PAGE 3 OF 4 FOR 208-240V GAS FRYERS MODEL: 718LCG ITEM NUMBERS: 21267-10, 21268-10 MODEL: 724CG ITEM NUMBERS: 21282-10, 21287-10 MODEL: 734CG ITEM NUMBERS: 21278-10, 21280-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 67
724G-1719_CV PAGE 4 OF 4 FOR 208-240V GAS FRYERS MODEL: 718LCG ITEM NUMBERS: 21267-10, 21268-10 MODEL: 724CG ITEM NUMBERS: 21282-10, 21287-10 MODEL: 734CG ITEM NUMBERS: 21278-10, 21280-10 TO IDENTIFY MODEL AND ITEM NUMBER, SEE DATA TAG INSIDE FRYER. IMPORTANT The electrical diagrams in this manual are for models produced 2018 and later with an ‘Omron’...
Page 69
Belshaw Adamatic Bakery Group Limited Warranty / Return Policy Subject to the terms and limitations set forth in this limited warranty (“Limited Warranty”), Belshaw Adamatic Bakery Group (also referred to as “the Manufacturer”) warrants to the original purchaser (“Purchaser”) of Manufacturer’s equipment and parts (“Products”), Belshaw Adamatic Bakery Group’s manufacture and assembly of Products to be free from defects in workmanship and material which would result in product failure under normal use and service.
Page 70
Warranty Claims In case of warranty claims relating to your Product, you must follow the instructions below. Report Claims to Your Authorized Distributor or Dealer or to Belshaw Adamatic Bakery Group As soon as you discover a problem, contact the Distributor or Dealer from whom you purchased the Product or Belshaw Adamatic Bakery Group.
Page 71
The #1 Source for Donut and Bakery Equipment www.belshaw.com BELSHAW ADAMATIC BAKERY GROUP 814 44th Street NW, Suite 103 Auburn, WA 98001 USA 1-800-BELSHAW 1-800-578-2547 (USA/Canada) (+1) 206-322-5474 (Worldwide) service@belshaw.com an Ali Group Company The Spirit of Excellence...
Need help?
Do you have a question about the 718LCG and is the answer not in the manual?
Questions and answers