CleanStation CSIIP Site Preparation Guide Contents 1 Introduction 1.1 About this Guide 2 Shipment and Delivery 2.1 Shipping Information and Responsibility 2.2 Shipping Size and Weight 2.3 Lifting Equipment 2.4 Unloading 3 Physical Description 3.1 Size and Weight 3.2 Tank Capacity 4 Site Requirements 4.1 Positioning / Clearance...
All site requirements must be met before the installation date. The Site Preparation Checklist should be sent to your Stratasys representative. Shipping will be arranged after the signed checklist is received by Stratasys. Non-compliance with requirements specified in this document might result in additional installation charges.
Shipment and Delivery Shipping Information and Responsibility Stratasys Ltd. will arrange shipment to the customer’s facility, as indicated in the “ship to” section of the invoice. It is the customer’s responsibility to provide Stratasys with detailed delivery instructions. The customer is also responsible for transporting the system to a suitably prepared installation location.
CleanStation CSIIP Site Preparation Guide Physical Description Figure 1 CleanStation CSIIP Size and Weight The following table shows the size and weight of CSIIP. Table 2 CSIIP Size and Weight W x H x D (cm) W x H x D (in)
CleanStation CSIIP Site Preparation Guide Site Requirements The following factors should be considered when choosing a suitable location for the CSIIP: • Clearance around and above the CSIIP to enable convenient access and servicing • Proximity to a water outlet and drain To avoid water damage to CSIIP, install CSIIP in another room or at least 5 meters (16.5 feet) away from the CSIIP.
CleanStation CSIIP Site Preparation Guide Power The customer must verify that an electrical outlet with the proper power specifications is available near the CSIIP. It is recommended that the electrical outlet be installed in back of the unit and higher than it, to reduce the chances of water spraying on the outlet.
CleanStation CSIIP Site Preparation Guide Environmental Requirements Temperature and Humidity The temperature and relative humidity around the CSIIP must be within certain limits. Peak conditions occur when the CSIIP draws maximum electrical power, resulting in the heat dissipation of 1010 Watts (3446 BTU/hr).
CleanStation CSIIP Site Preparation Guide Checklist Dear customer, After preparing your site for the installation of the CleanStation CSIIP Site Preparation Guide, please complete the customer information and the checklist below, and fax it to your Stratasys representative. Consult with your representative if you have any questions related to site preparation and the checklist.
Page 11
VeroCyan, VeroDent, VeroDentPlus, VeroGlaze, VeroGray, VeroMagenta, VeroWhitePlus, VeroYellow, Tango, TangoBlack, TangoBlackPlus, TangoGray, TangoPlus, Digital ABS and Digital ABS2 are trademarks or registered trademarks of Stratasys Inc., registered in the United States and other countries. ULTEM is a registered trademark of SABIC or affiliates. All other trademarks belong to their respective owners. Product specifications subject to change without notice. For more...
Need help?
Do you have a question about the CLEANSTATION CSIIP and is the answer not in the manual?
Questions and answers