Step 4.3 Performing final check and
trial operation
1 Check the following:
• Strength of the installation site
• Tightness of pipe connection to detect gas leak
• Electric wiring connection
• Heat-resistant insulation of the pipe
• Drainage
• Grounding conductor connection
• Correct operation (Take the following steps.)
2 Press the
(Power) button on the remote
control to check the following:
• The indicator on the indoor unit lights up.
• The airflow blade opens and the fan gears up
for operation.
3 Press the
(Mode) button to select Cool or Heat
mode. Then take the following sub-steps:
• In Cool mode, use the Temperature button to
set the set temperature to 16 °C.
• In Heat mode, use the Temperature button to
set the set temperature to 30 °C.
• Check whether, approximately 3 to 5 minutes
later, the outdoor unit starts, and a cool air
blows out.
• After 12 minutes of stationary condition, check
the indoor unit air treatment.
4 Press the
(Air swing) button to check whether
the airflow blades work properly.
5 Press the
(Power) button to stop the trial
operation.