Daikin Altherma M ECH2O Series Installation And Maintenance Instructions Manual page 36

Table of Contents

Advertisement

5
x
Start-up
1. Check the cold water connection and, where necessary, fill
the potable water heat exchanger.
2. Switch on the power supply to the Daikin Altherma M ECH
3. Wait for the start phase.
4. After the start phase has completed, in heating mode,
evacuate the heating system, check the installation pressure
and adjust if necessary (max. 3 bar, see chap. 7.4).
5. Carry out a visual inspection for leaks on all joints internally.
Seal any leaks that occur in a professional manner.
6. Set the rotary switch on the controller to the desired operating
mode.
7. If a Daikin
solar system is connected, commission it
according to the enclosed instructions. After shutting off the
Daikin
solar system, again check the fill level in the
buffer storage tank.
Installation and maintenance instructions
36
O.
2
Daikin Altherma M ECH
O
2
Solar storage tank with heating controller
008.1446799_00 – 07/2019 – EN

Advertisement

Table of Contents
loading

Table of Contents