Start-up
1. Check the cold water connection and, where necessary, fill
the potable water heat exchanger.
2. Switch on the power supply to the Daikin Altherma M ECH
3. Wait for the start phase.
4. After the start phase has completed, in heating mode,
evacuate the heating system, check the installation pressure
and adjust if necessary (max. 3 bar, see chap. 7.4).
5. Carry out a visual inspection for leaks on all joints internally.
Seal any leaks that occur in a professional manner.
6. Set the rotary switch on the controller to the desired operating
mode.
7. If a Daikin
solar system is connected, commission it
according to the enclosed instructions. After shutting off the
Daikin
solar system, again check the fill level in the
buffer storage tank.