Commissioning and testing

Before commissioning the appliance, the whole gas installation including the
meter must be purged and tested for gas soundness in accordance with BS
6891: 1988.
46
(Fortsetzung)
3. Insert the screw at the top of the
boiler.
Hinweis
The outer case forms a seal with
the combustion box. It must there-
fore be securely fitted with the
screw provided.