3. Modes of Operation
a). – Test timing set on the PCM500
In the PCM500 Test Point setup, enter the
number of tests to be performed in a test-
cycle and also include any delay between
individual tests. A test sequence can then be
started from the PCM500 or from the PLC.
If an additional test is required, whilst in a
test-cycle delay period, then the PLC can
initiate this, without compromising the
existing delay in the test-cycle setting.
Please be aware, the delay period entered
will start from the beginning of a test.
b). – Test timing set by the PLC
In the PCM500 Test Point setup, enter the
number of tests to 1 (one) and enable the
PLC to start a test at the appropriate time.
.