Safety; Equipment Inspection And Storage; Final Equipment Inspection; Mounting - ABB Zenith ZTSCT Series Operation And Maintenance Manual

Closed transition and bypass isolation closed transition automatic transfer switches, 100-4000 a
Table of Contents

Advertisement

Safety

Turn OFF all power before installation, adjustment, or removal of transfer switch or any of its components.
The safe operation of your switch is ABB Zenith's focus.
The proper storage, installation, operation and maintenance
will help increase the life of the switch.
CAUTION
Due to hazardous voltage and current,
recommends that an
ABB
or a qualified electrician must perform the
installation and maintenance of the switch.
Equipment Inspection
and Storage
Once you have received the transfer switch, inspect it for
any damage. This includes damage to the enclosure, power
panel, control panel and wiring harness. If any damage
is found or suspected, file a claim as soon as possible with
the carrier and notify the nearest ABB Zenith representative.
Before installation, if it is necessary, store the transfer
switch in a clean dry place, protected from dirt and water.
Provide ample air circulation and heat, if necessary, to
prevent condensation.
Operating
Storage
Temperature
Temperature
(Ambient):
40-400 AMP
-30°C to
+75°C
(molded shell)
(-22°F to
-20°C to +65°C
+167°F)
(-4°F to +149°F)
40-4000 AMP
(all other frame
and panel types)
-20°C to +60°C
(-4°F to +140°F)

Final Equipment Inspection

Prior to energizing the transfer switch:
1.
Remove any debris incurred, with a vacuum,
due to shipment or installation.
2.
Verify that all cabled connections are correct
and that phase rotation of both sources match.
WARNING
Do not use a blower since debris may
become lodged in the electrical and
mechanical components and cause damage.
ABB Zenith
DANGER
HAZARDOUS VOLTAGE
(Can Cause Severe Injury or Death)
Zenith
ABB
Zenith Certified technician
Humidity
5% to 95%
(non-con-
densing)
ZTSCT / ZBTSCT Operation & Maintenance Manual
3.
Check engine start connections.
4.
Verify the correct connection of all control wires.
5.
Check settings of all timers and adjust as necessary.
6.
Adjust any optional accessories as required.
7.
Check the lug torque values of the power
connections.
:
Lug torque values are specified
NOTE
in table 2 on pg.2.
8.
Make sure that all covers and barriers are
installed and properly fastened.
:
Power panels ship from ABB Zenith
NOTE
in Source 1 Position.
Each ABB Zenith transfer switch is factory wired and
tested. A complete information package is furnished
with each switch which includes:
a.
Sequence of operation.
b.
Description and operation of all accessories
supplied.
c.
Power panel connection diagram and schematic.
d.
Description and identification of all customer
field connections.
Installation of ABB Zenith transfer switches includes:
a.
Mounting the transfer switch cabinet.
b.
Connection of Source 1, Source 2,
and Load cables or bus bars.
c.
Connection of external control circuits as required.

Mounting

Adequate lifting means must be used to mount the transfer
switch into place. The recommended method for moving
the transfer switch using the lifting eyes, where supplied,
and a spreader bar is illustrated in Figure 1. Enough room
should be allowed to open the cabinet doors fully for
inspection and servicing of the switch per NEC and
local codes.
CAUTION
Before drilling conduit entry holes or any
accessory mounting holes, cover and protect
the switch and control panel to prevent dirt
and metal fragments from entering the
mechanical and electrical components.
Failure to do so may result in
damage and malfunction of the switch.