Connecting Pipes to the Indoor Unit
• Preparation of Piping
Main cause of gas leakage is defect in flaring
work. Carry out correct flaring work in the
following procedure.
1) Cut the pipes and the cable.
• Use the accessory piping kit or the pipes
purchased locally.
• Measure the distance between the indoor and
the outdoor unit.
• Cut the pipes a little longer than measured
distance.
• Cut the ca ble 1.5m longer than the pipe
length.
2) Burrs removal
• Completely remove all burrs from the cut
cross section of pipe/tube.
• Put the end of the copper tube/pipe to
downward direction as you remove burrs in
order to avoid to let burrs drop in the tubing.
3) Putting nut on
• Remove flare nuts attached to indoor and
outdoor units, than put them on pipe/tube
having completed burr removal.
(Not possi ble to put them on after flaring
work)
4) Flaring work
• Carry out flaring work using flaring tool as
shown below.
Outside diamete r
mm
Ø6.35
Ø9.52
Ø12.7
Ø15.88
Ø19.05
Fi rmly hold copper tube in a bar(or die) as
indicated dimension in the table above.
5) Check
• Compare the flared work with figure below.
• If flare is noted to be defective, cut off the
flared section and do flaring work again.
A
inch
mm
1/4
0.5~0.8
3/8
0.5~0.8
1/2
0.5~0.8
5/8
0.8~1.0
3/4
0.8~1.0
Copper
tube
90°
Point down
Copper tube
Bar
Bar
"A"
Copper pipe
Clamp handle
Smooth all round
Inside is shining without scratches
Inclined
Even length
all round
Installation
Slanted Uneven Rough
Pipe
Reamer
Flare nut
Handle
Yoke
Cone
Red arrow mark
= Improper flaring =
Surface
Cracked Uneven
damaged
thickness