Seeley AIRA ATH Series Installation, Operation & Service Manual page 23

Vacuum assisted linear, double linear, u-tube, and multi-burner gas fired heating systems
Table of Contents

Advertisement

A
ATH I
O
IRA
NSTALLATION
PERATION AND
Step 6.4.1 Coupling and Tube Assembly (Continued)
Tighten slide bar as shown below.
Correct Slide Bar
dimensions
• Repeat Step 6.4 A - D until all tubes are assembled. See Page 20, Section 6.4.2 shown below.
Step 6.4.2 Coupling and Tube Assembly (Continued)
20 of 73
S
M
ERVICE
ANUAL
Drive slide bar until tight.
End of slide bar should be
within tolerance listed below.
± 50 mm
Incorrect Slide Bar
position
Model
Overall Tube Length (mm)
ATH15ST
ATH20ST
ATH25ST
ATH30ST
12,000
ATH35ST
12,000
ATH40ST
12,000
ATH45ST
15,000
ATH50ST
15,000
Number
of Tubes
6,000
2
9,000
3
9,000
3
4
4
4
5
5