DRAFT DGA-LT1 Installation Guide
Monitor Installation 
CAUTION: Do not attempt to install your DGA‐LT1 On‐Line Transformer Monitor until you have read and fully 
understand the procedures outlined in this document. 
Installation of the DGA‐LT1 consists of the following: 
Site Preparation    
Mounting the Monitor 
Mounting the Gateway 
Bleeding Air from the Monitor 
Configuration 
Site Preparation 
 NOTE: Qualitrol recommends a minimum size of 1" for the transformer oil supply valve and a minimum of 3" vertical 
clearance between the valve centerline and the transformer foundation for proper installation space. 
Ensure the following prior to mounting the monitor: 
An adequate valve location for mounting the DGA‐LT1 monitor has been identified  
Transformer is oil‐filled and a baseline Dissolved Gas Analyzer sample has been taken to provide 
baseline levels for Hydrogen concentration and Oxygen concentration for use in configuration of the 
system 
All shipped items have been located 
 
The following tools are required for installation of the DGA‐LT1 monitor: 
Adjustable wrench and/or pipe wrench 
Teflon tape and pipe‐thread sealant 
Container to collect oil during installation 
Note that installation of the sensors and gateway should take place from transformer closest to the cellular 
gateway location outwards to ensure that a communication path has been established for commissioning of 