Example of Procedure
Action
Response
Set the start mode selector on the
1.
Processor Module PM511 front in 3 (CLEAR)
2.
Check that the program card is in position.
The system software will be reloaded at the
cold start.
3.
Depress the ENTER button
4.
Set the start mode selector in 1 (AUTO)
Do not press the ENTER button!
5.
Connect the communication cable between
the engineering station and the Processor
Module PM511, port X10.
6.
Switch on the power supply to the
engineering station
If necessary start Application Builder in
7.
AdvaBuild window to select project and
node.
8.
Start On-line Builder from within the
Application Builder or in AdvaBuild
window.
9.
Press <Ctrl>, <Break>
to activate the engineering tool.
10. Select 1 (Advant Controller 400) <CR>
11. Select 1 (Advant Controller 400 programming)
<CR>
12. In the node Setup window confirm or
select the correct Target System.
13. Type LDIR SRCE:*.AD<CR>to
check that your DUAP dump is available.
14. Type LOAP <dump name>, SRCE <CR>
For example LOAP ABCD, SRCE<CR>
15. DICONFIG <CR>
16. Type Y <CR>
The processor module will now indicate P1 (OPERATION mode) on the character display.
®
Advant
Controller 450 User's Guide
Section 5.5.17 Loading of Application Program
The controller system configuration and the
application program are erased.
The processor module will indicate P2 after
about a minute.
Successful Advant Station 100 Series ES
boot Windows start up.
Appropriate node found.
Booting engineering board
Press <Ctrl>, <Break>
Contact with target.
Identity presented.
In the example the following
ABCD0001.AD
ABCD0002.AD etc.
are listed.
The loading proceed. #
OK TO START UP THE TARGET, Y/N
After about one minute:
THE TARGET SYSTEM IS NOW IN
OPERATION MODE