Closing shutoff valve

1. Remove the cap and turn the valve clockwise with the hexagon wrench.
2. Securely tighten the valve until the shaft contacts the main body seal.
3. Make sure to tighten the cap securely.
* For the tightening torque, refer to the table on the below.

Tightening torque

Outside diameter
mm
Ø6.35
Ø9.52
Ø12.7
Ø15.88
Ø19.05

HEAT INSULATION

1. Use the heat insulation material for the refrigerant piping which has an excellent heat-resistance
(over 248°F).

2. Precautions in high humidity circumstance:

This air conditioner has been tested according to the
"ISO Conditions with Mist" and confirmed that there is
not any default. However, if it is operated for a long
time in high humid atmosphere (dew point tempera-
ture: more than 73°F), water drops are liable to fall. In
this case, add heat insulation material according to the
following procedure:
• Heat insulation material to be prepared... EPDM
(Ethylene Propylene Diene Methylene)-over 248°F
the heat-resistance temperature.
• Add the insulation over 10mm thickness at high humidity environment.
Torque
N . m(kgf
inch
1/4
18~25(180~250)
3/8
34~42(340~420)
1/2
55~66(550~660)
5/8
63~82(630~820)
3/4
99~121(990~1210)
Indoor unit
cm)
Installation Manual 19
Installation
Fastening band
(accessory)

Refrigerant piping

Thermal insulator