Step 2 - Make Duct Connections; Step 3 - Connect Power Wiring - Carrier 45J Installation, Start-Up And Service Instructions Manual

Fan powered variable air volume terminals
Table of Contents

Advertisement

unit, low voltage controls from the side and line voltage
motor controls or electric heat (if equipped) from the rear
(discharge end) of the unit.
Bottom access panel removal requires a minimum of 3-in.
minimum clearance, plus substantial horizontal clearance
to slide the access panel out of the way for service. Actual
horizontal dimensions will vary due to varying access pan-
els for different sized units. See your particular unit's sub-
mittal drawings for more detail.
NOTE: Be certain appropriate accommodations for panel
removal of most unit casings are large enough to allow ad-
equate internal service room once the panels are removed.
A clearance of 18-in. is recommended for control enclosure
access. Unit control enclosure will vary depending on
which control package is used. Control enclosure location
is specified on unit submittals. Low voltage enclosure cov-
ers are removable, not hinged.
A clearance of 36-in. is recommended for line voltage mo-
tor controls and electric heat control access. High-voltage
motor controls or electric heat control access is supplied
with hinged access doors for units with fused disconnect.
Specific location is indicated on the unit submittal.
NOTE: These recommendations do not supersede NEC
(National Electrical Code) or local codes that may be appli-
cable, which are the responsibility of the installing contrac-
tor.
4. Whenever possible, fan-powered boxes should be installed
over halls or passageways (rather than over occupied spac-
es) in order to limit the sound reaching occupants.
POSITION UNIT
1. When moving boxes, use appropriate material handling
equipment and avoid contact with shaft extensions, con-
trols, wiring, piping, heaters, and control boxes.
2. Raise unit to position using safe mechanical equipment and
support until hanging means are attached and box is level.
INSTALL UNIT
1. Install field-supplied eye bolts, strap hangers or bolt rod
supports as desired. Figure 6 illustrates possible unit sus-
pension methods. A typical installation is shown in Fig. 7.
2. Care should be taken to use hanging materials of sufficient
stiffness and strength, rigidly attached to the unit. Straps
should not be located on coil flanges, electric heat sections,
or control boxes. When using trapeze supports, avoid areas
where access is required to side mounted controls, or side
or bottom access doors. For best installation with trapeze
supports, provide elastomeric material between unit and
supports.
3. Hangers should be securely attached to bar joist or mount-
ing anchors properly secured to building structure with lugs
or poured-in-place hangers. Percussion nails are not con-
sidered adequate anchors.
Step 2 — Make Duct Connections
1. Install supply ductwork on each of the unit inlet collars. It
is recommended that 3 duct diameters of straight duct are
supplied to the inlet of the unit. An elbow put at the inlet of
the unit will create turbulence at the inlet making it difficult
for the flow sensor to accurately measure the airflow.
Check that the pressure pick-up in primary air collar is lo-
cated properly and that air supply duct connections are air-
tight. Install supply ductwork on unit inlet collar, following
all accepted medium-pressure duct installation procedures.
Seal joints against leakage.
NOTE: For maximum efficiency in controlling radiated noise in
critical applications, inlet ducts should be fabricated of 24-gage
minimum sheet metal in place of flex connections. Flex duct is
extremely transparent to radiated sound; consequently high inlet
statics (Ps) or sharp bends with excessive pressure drop can
cause a radiated noise problem in the space. If flex duct is used,
it should be limited to the connection between the distribution
duct and the boot diffuser.
2. Install the discharge duct. On units with electric heat, the
recommended minimum distance of straight duct before
any transitions, elbows or branch connections is 48 inches.
It is strongly recommended that lined discharge duct be
used downstream of the unit. Insulate duct as required.
3. Fan boxes should not be attached to octopus sections im-
mediately downstream of the unit.
4. Install optional return-air filters before operating the unit.
5. Where construction filters were supplied with the box,
leave filters in place until installation is complete and
building is cleaned for occupancy.
Step 3 — Connect Power Wiring (See Fig. 8)
1. All power wiring must comply with local codes and with
the NEC (National Electrical Code) ANSI/NFPA (Ameri-
can National Standards Institute/National Fire Protection
Association) 70-2017. Disconnect switches are optional
equipment. Electrical, control and piping diagrams are
shown on the exterior labeling or on a diagram inside the
control and high-voltage enclosure covers, unless other-
wise specified in the order write-up. All units are wired for
a single point electrical connection to the fan and electric
heater (if equipped). Electric heaters provided by Carrier
are balanced by kW per stage. The installing electrician
should rotate incoming electric service by phase to help
balance overall building load.
2. All field wiring must be provided with a safety disconnect
per NEC 424-19, 20, and 21.
3. Disconnect all incoming power before wiring or servicing
unit. All disconnect switches on the terminal (if equipped)
should be in the OFF position while making power connec-
tions.
4. Units with electric heat should use copper wires rated at
least 125% of rating plate amperage. Refer to the unit's rat-
ing label and minimum supply circuit amps.
5. Observe wiring diagram and instructions attached to the
unit. The 480-v, 3-phase units require a Wye power source
with a fourth (neutral) wire in addition to the full sized
ground wire. All units must be grounded as required by
NEC 424-14 and 250.
5