Test Operation - Sakata SOB-50VA Service Manual

Light commercial air conditioner r410a on/off
Table of Contents

Advertisement

Light Commercial R410A on-off

Test Operation

7.
(1) The test operation must be carried out after the entire installation has been completed.
(2) Please confirm the following points before the test operation.
The indoor unit and outdoor unit are installed properly.
Tubing and wiring are correctly completed.
The refrigerant pipe system is leakage-checked.
The drainage is unimpeded.
The ground wiring is connected correctly.
The length of the tubing and the added stow capacity of the refrigerant have been recorded.
The power voltage fits the rated voltage of the air conditioner.
There is no obstacle at the outlet and inlet of the outdoor and indoor units.
The gas-side and liquid-side stop values are both opened.
The air conditioner is pre-heated by turning on the power.
(3) According to the user's requirement, install the remote controller when the remote controller's
signal can reach the indoor unit smoothly.
(4) Test operation
Set the air conditioner under the mode of "COOLING" with the remote controller, and check the following
points.
Indoor unit
Whether the switch on the remote controller works well.
Whether the buttons on the remote controller works well.
Whether the air flow louver moves normally.
Whether the room temperature is adjusted well.
Whether the indicator lights normally.
Whether the temporary buttons works well.
Whether the drainage is normal.
Whether there is vibration or abnormal noise during operation.
Outdoor unit
Whether there is vibration or abnormal noise during operation.
Whether the generated wind, noise, or
neighborhood.
Whether any of the refrigerant is leaked.
Installation
condensed of by the air conditioner have influenced your
S13-01.01.13en
118

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents