Rheem RBHP-17A00NH1 Installation Instructions Manual page 13

Rbhp series multiposition air handler
Table of Contents

Advertisement

FIGURE 5
ROTATING CIRCUIT BREAKER
IMPORTANT: To comply with certification agencies and the National Electric
Code, units with circuit breaker(s) on vertical units must have circuit breakers
installed so that the breaker switch "on" position and marking is up and, "off"
position and marking is down.
- To turn breaker(s): Rotate one breaker pair (circuit) at a time starting with the one on the
right. Loosen both lugs on the load side of the breaker. Wires are bundles with wire ties,
one bundle going to the right lug and one bundle going to the left lug.
- Using a screwdriver or pencil, lift white plastic tab with hole away from breaker until
breaker releases from mounting opening (see Figure 5).
- With breaker held in hand, rotate breaker so that "on" position is up, "off" position is down
with unit in planned vertical mounting position. Insert right wire bundle into top right
breaker lug, ensuring all strands of all wires are inserted fully into lug, and no wire insula-
tion is in lug.
- Tighten lug as tight as possible while holding circuit breaker. Check wires and make sure
each wire is secure and none are loose. Repeat for left wire bundle in left top circuit
breaker lug.
- Replace breaker by inserting breaker mounting tab opposite white pull tab in opening,
hook mounting tab over edge in opening.
- With screwdriver or pencil, pull white tab with hole away from breaker while setting that
side of breaker into opening. When breaker is in place, release tab, locking circuit break-
er into location in opening.
- Repeat above operation for remaining breaker(s) (if more than one is provided).
- Replace single point wiring jumper bar, if it is used, on line side of breaker and tighten
securely.
- Double check wires and lugs to make sure all are secure and tight. Check to make sure
unit wiring to circuit breaker load lugs match that shown on the unit wiring diagram.
• Electrical connections can be made from either the left or right side of the unit.
Refrigerant and condensate drain connections are made on the front of the unit (see
Figure 4).
• RXBB-AA combustible floor base is used for all unit sizes. Unit must be centered on
combustible base in the width dimension (14
WARNING
THE RXBB-AA COMBUSTIBLE FLOOR BASE IS REQUIRED WHEN SOME
UNITS WITH ELECTRIC HEAT ARE APPLIED DOWNFLOW ON COMBUSTIBLE
FLOORING. FAILURE TO USE THE BASE CAN CAUSE A FIRE RESULTING IN
PROPERTY DAMAGE, PERSONAL INJURY OR DEATH. SEE CLEARANCES
FOR UNITS REQUIRING A COMBUSTIBLE FLOOR BASE.
3
/
").
8
13