Allied Air A80UH1E Installation Instructions Manual page 13

Warm air gas furnace upflow / horizontal left and right air discharge
Table of Contents

Advertisement

HORIZONTAL LEFT POSITION
Top Vent discharge
Disconnect pressure switch hose from barbed fitting on the pressure
switch assembly. Remove pressure switch assembly (1 screw) and
cut wire tie to free pressure switch wires. Reinstall pressure switch
on the other side of orifice plate and reconnect pressure switch hose.
Resecure pressure seitch wires: Either pull excess wires through the
blower compartment and secure using supplied wire tie, or coil excess
wire and secure to the gas manifold.
Figure 19
HORIZONTAL LEFT POSITION
Side Vent Discharge
Cut combustion air inducer tubing from 9" to 7" to avoid interference
with inducer motor.
Disconnect pressure switch hose from barbed fitting on the pressure
switch assembly. Remove pressure switch assembly (1 screw) and
cut wire tie to free pressure switch wires. Reinstall pressure switch
on the other side of orifice plate and reconnect pressure switch hose.
Resecure pressure seitch wires: Either pull excess wires through the
blower compartment and secure using supplied wire tie, or coil excess
wire and secure to the gas manifold.
Figure 20
507330-01
HORIZONTAL RIGHT POSITION
Gas supply piping must be brought into the unit from the bottom in order
to accommodate the flue pipe.
Cut combustion air inducer tubing from 9" to 8" to avoid interference with
inducer motor.
Remove make-up box assembly (2 screws) and cut wire tie to free make-
up box wires. Reinstall make-up box on other side of cabinet.
Resecure make-up box wires: Either pull excess wires through the blower
compartment and secure using supplied wire tie, or coil excess wire and
secure to the gas manifold.
HORIZONTAL RIGHT POSITION
Issue 1624
Top Vent Discharge
Figure 21
Side Vent Discharge
Figure 22