Ducane CMP A Series Installation Instructions Manual page 6

Table of Contents

Advertisement

1. In series
flow applications,
the coil is mounted after the
furnace in an enclosure in the supply air stream. The furnace
blower is used for both heating and cooling airflow.
2.
In parallel flow installation, dampers
must be provided to
direct air over the furnace heat exchanger when heat is desired
and over the cooling when cooling is desired.
IMPORTANT:
The dampers should be adequate to prevent
cooled air from entering
the furnace, and if
manually
operated,
must
be equipped
with
means to prevent operation of either the cooling
unit or furnace unless the damper is in the full
cool or full heat position.
WARNING
The coil MUST
be installed
on the air discharge
side of the furnace.
Under no circumstances
should
the air flow be such that cooled, conditioned
air can
pass over the furnace
heat exchanger.
This will
cause
condensation
in the
heat
exchanger
and
possible
failure ,of the heat exchanger
that could
lead to a fire hazard
and/or hazardous
conditions
that may lead to bodily
harm.
Heat exchanger
failure
due to improper
installation
may not be
covered by warranty.
Gas piping shall be of such size and so installed as to provide
a supply of gas sufficient to meet maximum demands without
undue loss of pressure between the gas meter and the furnace. It is
recommended that the gas line to the furnace shall be a separate
line direct from the meter, unless the existing gas line is of ample
capacity. Refer to gas pipe capacity table in the National Fuel Gas
Code (ANSI 7-,223.1) or the CANI-B 149 Installation Code.
Use a joint compound (pipe dope) that is resistant to the action
of liquefied petroleum gases or any other chemical constituents of
the gases to be conducted through the piping.
NOTE:
In order to make proper input adjustments, minimum and
maximum gas supply pressure limits shown on the rating
plate must not be exceeded.
Before any system of gas piping is finally put into service, it
should be carefully tested to determine if it is gas tight. Check all
piping for leaks using soapy water and a brush. The piping must
stand a pressure of six (6) inches of mercury for a period of ten
(10) minutes or as required by local authority.
WARNING
The furnace and its individual shutoff valve must
be disconnected
from the supply piping system
during any pressure testing of that system at test
pressures
in excess
of
1/2 PSIG
(3.5kPa
or
14"w.c.).
The furnace
must be isolated
from the gas supply
piping
system
by closing
its
individual
manual
shutoff
valve
during
any pressure
testing
of the
gas supply
piping
system
at pressures
equal
to or
less than 1/2 PSIG (3.5kPa
or 14"w.c.).
Failure to
follow
the
above
procedures
couId
lead
to
a
hazardous
condition
and bodily
harm.
o
Figure 1.6
GAS CONNECTION METHODS
,_LTS
r•
,
FIELD
SHUT OFF
VALVE
l'
I_ DRIP tea
FIELD INSTALLED
GROUND
UNION
This furnace is manufactured for use with Natural gas and
must be converted using the proper LP conversion kit for use with
LP (Propane) gas.
For LP (Propane) gas, a tank regulator is
required to reduce supply pressure to 12"-13"w.c.
For manifold
pressure, see Table 2.13.
A main manual shut off valve must be used in the gas piping.
The shut off type and location must follow local codes and should
always be in an accessible but protected location. In the absence
of local codes the _conm_nded
methods for installing the gas
piping to the furnace are shown in Figure 1.6.
The gas valve contains two threaded ports for a 1/8" NPT tap
in order to test incoming gas pressure and outgoing manifold
pressure (See Figure 1.12).
CAUTION
Many soaps used for leak testing are Corrosive to
certain metals.
Piping must be rinsed thoroughly
with
clean
water
after
leak
check
has
been
completed.
WARNING
Never
use an open flame when testing for gas
leaks!
Use of an open flame could lead to a fire or
explosion.
20246506
Issue 9939
Page 6 of 22

Hide quick links:

Advertisement

Table of Contents
loading

Related Products for Ducane CMP A Series

Table of Contents