1-1 Introduction The SunWide is an advanced design using a microcontroller for digital accuracy and fully automatic operation. Each model unit can be used for 12V, 24V and 48V system and can be operated at three major functions including solar charging, load control and lighting control.
1-3 Specifications MODEL SW-10CL SW-20CL SW-30CL SW-45CL ELECTRICAL System voltage ratings 12, 24, 48 Vdc Current ratings-Battery Charge Control Current ratings-Load Control/ Lighting Control 12/24V:≦0.1 % ± 50 mV Accuracy 48V:≦0.1 % ± 100 mV Min. voltage to operate Max. solar array Voc 140 V Max.
Page 4
1-4 SW-10CL, SW-20CL, SW-30CL Mounting Dimension Unit: mm OFF 2 SunWide CHARGE LOAD Normal Voltages SW-30CL 12V -24VDC BULK ABSOR FLOAT LIGHTING EQUAL CONTROL FAULT FAULT SOLAR BATTERY LOAD Remote Panel MANUAL LIGHT TEST EQU/LVR Length Model SW-10CL / SW-20CL...
1-6 Installation Overview The installation is straight forward but it is important that each step is done correctly and safely. A mistake can lead to dangerous voltage and current levels. Be sure to carefully follow the following instructions for all the terminal connection. Charge Load Lighting...
Page 6
ON: Lighting control Dip Switch 7 OFF: Load Control Lights remain turned off. OFF: 2,4,6,8,10: Hours light is turned on after sunset. Light is turned on after sunset, turned off after the selected 2/1, 3/1, 4/1, Lighting control lasting hours, and turned on again before sunrise. 6/1, 2/2, 3/2, Switch 2/1: Light is turned on for two hours after sunset, turned off...
Page 7
Push Buttons Press the Light Test Push Button to enter the testing mode to check if the Lighting Control Switch has been correctly set in order to control the lights based on desired timer. Procedure: Light Test 1. Select Dip Switch 7 to be ON 2.
1-7 Installation Steps: This section provides a brief overview of how to get started using the SunWide controller. However, please review the entire manual to ensure best performance and years of trouble-free service. NOTES: The SunWide prevents reverse current leakage at night, so a blocking diode is not required in the system.
Page 9
connected during the daytime and the array is wired correctly. ※ If the SOLAR is disconnected during installation, the controller will see this as the first night and the length of night will be too short. This will only affect ON/OFF/ON settings, and will automatically be corrected over 4 days.
2-1 Operating Modes There are three distinct operating modes programmed into each SunWide. Different from SunStar, only one mode of operation being selected for an individual unit, SunWide can be operated at Solar Battery Charging mode and DC Load Control or Lighting control mode at the same time.
Page 11
Four Stages of Solar Charging EQUALIZE ABSORPTION BULK FLOAT CHARGING NIGHT NIGHT TIME Solar Charging Stages 1. Bulk Charging: In this stage, the battery will accept all the current provided by the solar system. 2. PWM Absorption: When the battery reaches the regulation voltage, the PWM begins to hold the voltage constant.
Page 12
Battery Types: The SunWide’s standard battery charging programs are suitable for a wide range of lead-acid battery types. These standard programs are select by DIP Switch 3~5. Standard Battery Charging Programs The SunWide provides 8 standard battery charging algorithms (programs) that are selected with the DIP switches.
Page 13
F. Equalization Interval–Equalizations are typically done once a month. Most of the cycles are 28 days so the equalization will begin on the same day of the month. It can be set by Dip Switch 3~5 for different interval days. Each new cycle will be reset as the equalization starts so that a setting day period will be maintained.
Page 14
10ºC / 50ºF + 0.45 V + 0.90 V + 1.80 V 5ºC / 41ºF + 0.60 V + 1.20 V + 2.40 V 0ºC / 32ºF + 0.75 V + 1.50 V + 3.00 V Temperature Compensation Equalization Routine equalization cycles are often vital to the performance and life of a battery — particularly in a solar system.
Page 15
Standard Equalization Programs Both automatic and manual equalizations can be performed using the standard charging programs. Manual Equalization The SunWide is shipped with the DIP switch set for manual equalization only. This is to avoid an unexpected or unwanted automatic equalization. In the manual mode, the pushbutton is used to both start or stop a manual equalization.
Page 16
The battery manufacturer can recommend the specific gravity or voltage values for your particular battery. Float When a battery becomes fully charged, dropping down to the float stage will provide a very low rate of maintenance charging while reducing the heating and gassing of a fully charged battery.
2-3 Adjustability of Load Control When setting in the load control mode, DIP Switch 7 should be placed at OFF. The LVD (low voltage disconnect) and LVR (low voltage reconnect) are important setpoints to protect the system battery from deep discharges that could damage the battery. The Procedure of LVD/LVR Selection Step 1: Press MANUAL EQU/LVR push button and LIGHT TEST push button at the same time until the CHARGE LED turns red and LOAD LED turns green in...
Page 18
• a power diode • rated equal or greater than 80 volts • rated equal or greater than 10 amps (SW-10CL) or 20 amps (SW-20CL) or 30 amps (SW-30CL) For large inductive loads, a heat sink for the diode may be necessary.
Page 19
2-4 Adjustability of Lighting Control When setting in the lighting control mode, DIP Switch 7 should be placed at ON. After completing the system connections, select the desired LIGHTING CONTROL switch option. The brief description of the options follows below: Lights remain turned off.
Page 20
LIGHT TEST Button Press the LIGHT TEST button to enter the testing mode to check if the Lighting Control Switch has been correctly set in order to control the lights based on desired timer. The procedure is listed as below. STEPS: 1.
2-5 Troubleshooting The SunWide is very rugged and designed for the most extreme operating conditions. Most PV system problems will be caused by connections, voltage drops, and loads. Troubleshooting the SunWide controller is simple. Some basic troubleshooting procedures are listed below. CAUTIONS: 1.
Page 22
troubleshooting the problem. Check that the load is turned on. Check that no system fuses are defective. Check that no system circuit breakers are tripped. Remember that there are no fuses or circuit breakers inside the SunWide. Check connections to the load, and other controller and battery connections. Make sure voltage drops in the system wires are not too high.
Need help?
Do you have a question about the SW-10CL and is the answer not in the manual?