Getting Started - Krell Industries Foundation 4K Owner's Reference Manual

Table of Contents

Advertisement

Getting Started

Unpacking and Placement
The Foundation 4K UHD Processor is a precision instrument and should be handled with the utmost care when
deciding where it is to be placed and while it is being unpacked and finally installed. Makes sure installation
location is dry and level, and able to provide adequate ventilation. The Foundation 4K UHD Processor runs warm
to the touch and requires the bottom and top of the unit be free from obstruction with good circulation of air.
Allow a minimum of 3 inches above the unit for proper ventilation. Additional ventilation may be required when
the unit occupies the same space with other electronics that generate heat like power amplifiers. Please consult an
authorized KRELL dealer or KRELL industries to insure proper installation guidelines.
1. Accessories included
A. 1 AC Power cord
B. 1 Handheld Remote control
C. 1 Trigger cable
D. 1 CD w/ Owner's reference
E. 1 Warranty registration card
F. 2 AAA Batteries
G. 1 T-10 torx wrench
AC Power Guidelines
The Foundation 4K UHD Processor is designed to work all over the world. The operating voltage is determined at
the factory and is specifically set to operate in the country of final destination. The Foundation 4K UHD Processor
requires good clean power and doesn't require additional filtration.
NOTE: The Foundation 4K UHD Processor may not operate correctly when AC regeneration or voltage conversion
devices are utilized.
Foundation 4K UHD Processor