D2 Lite Enclosure Testing
The D2 Lite enclosure needs be tested after it is installed and prior to
activating the first customer on each SWiM module. Testing should
take place after the homerun wiring is completed and the power
inserter is installed and powered on. These steps can also be used to
troubleshoot the D2 Lite system.
SWiM #1
In the unit
Run EIV+ at the SIGNAL TO IRD port on the power inserter
If EIV+ fails troubleshoot issue to resolution
At the D2 Lite enclosure
Run EIV+ at APMT FEEDs 2,3,4 (assumes APMT FEED 1 is connected to the homerun
and power inserter)
If EIV+ fails at any port, replace D2 Lite enclosure
DO NOT ATTEMPT TO REPLACE ANY COMPONENTS IN THE D2 Lite enclosure
SWiM #2 (if installed)
Same as SWiM #1 using APMT FEEDs 5,6,7,8