Recommissioning the heating system

This section describes the commissioning procedure
using the programming unit's basic control panel.
To ensure safe operation of the heating system and to test
specific performance indicators, the burner/gas valve unit
fitted in the boiler have been factory-tested as described
in detail in ANSI Z21.13 and CGA 4.9.
Danger: Risk of fatal injury from electric cur-
rent when appliance is opened up.
V Before opening the boiler:Disconnect the
heating system from the electrical power
supply by means of the emergency stop
switch or the relevant circuit breaker on
the main fuse board.
V Take measures to ensure the heating sys-
tem can not be switched on again uninten-
tionally.
V After completing the work described below, fill out the
commissioning log (
Section 7.20, page 54).
Caution: Risk of boiler damage due to ex-
cessive dust and airborne debris levels.
V Do not operate the boiler when there is a
lot of dust in the boiler room, e.g. due to
building work.
V An air filter must be fitted if the supply of
combustion air contains large quantities of
dust (e.g. from unpaved roads and tracks
or dusty workplaces such as quarries,
mines, etc.) or airborne seeds from plants.
Warning: Risk of boiler damage from con-
taminated combustion air.
V Do not use cleaning agents that contain
chlorine or halogenated hydrocarbons
(e.g. in spray cans, solvents and cleaning
agents, paints, glues).
V Do not store or use such substances in
the boiler room.
V If the burner has become dirty as a result of
building work, it must be cleaned before being
commissioned.
V Inspect flue and combustion air piping and the
vents for combustion air supply and ventilation
(
Section 5, page 20).
Logano plus GB312 - Technical specifications are subject to change without prior notice
Recommissioning the heating system
Read the following carefully before switching on so
as to avoid potentially fatal situations:
Danger: Risk of fatal injury due to failure to
follow the commissioning instructions and
consequent incorrect operation.
V If these instructions are not followed ex-
actly, a fire or explosion may be caused re-
sulting in serious damage to property,
serious injury or loss of life.
V It is imperative that the commissioning in-
structions are followed!
Danger: Risk of explosion
If you smell gas there is a danger of explo-
sion!
V Extinguish all naked flames. Do not smoke.
V Avoid creating sparks.
Do not operate any electrical switches or
equipment such as telephones, power
plugs and doorbells!
V Turn off the gas cock!
V Open windows and doors!
V Do not operate any electrical switches.
V Warn other occupants of the building!
V Leave the building.
V From outside the building, call gas com-
pany, heating installer or fire department.
Danger: Risk of fatal injury due to water
damage.
V The appliance must not be used if any part
of it has been under water.
V Have the appliance checked by a qualified
service contractor.
V Any parts of the programming unit or the
gas valve that have been under water must
be replaced by a qualified service contrac-
tor.
7
41