Step 3
: Installing the Window
The following steps provide details for structural fastening of the window to the opening. When installing windows
with nailing fin or wood brick mould casing, it may be desirable to first attach the window using these fastening
methods in conjunction with steps 1−5. Then complete the installation by fastening with structural brackets or
screws. Always follow fastener spacing outlined in the "Jamb/Sill Screw Chart" section. On applicable construction
using a continuous air barrier system, prepare the opening before installing the window. Refer to the "Continuous
Air Barrier Systems" section for details.
(a)
Figure 6: Plumb and square unit. (Illustration shows both structural bracket and jamb screw installation.)
Seek Assistance: Some large windows
and/or assemblies are very heavy. Avoid
injury by getting help to lift and position the
window into the rough opening.
1. If rigid sill pan is not used, pan sill with alternate meth-
ods or shim under window sill to ensure it does not
come in direct contact with treated lumber.
2. On some larger units such as the Ultimate Double
Hung Magnum, it may be necessary to remove the
sash prior to installation. See the sash removal sec-
tion for details.
3. Center the window in the opening. Level at the sill
and plumb the frame (interior/exterior) to desired
depth.
4. Fasten and shim the jambs at the bottom with the
appropriate fastener (follow instructions in the
"Fastening Methods" section). See figure 6a.
NOTE: Some units such as the Ultimate Double Hung
Magnum and IZ3 Ultimate Double Hung, feature unique
fastening systems. For these windows refer to the "Spe-
cial Fastening Systems" section for details.
19970019
2012−04−10
Measure
diagonally
for square
(b)
5. Fasten and shim at the top corners to square the unit
in the opening. Take diagonal measurements of the
window. When equal, the window is square in the
opening. Adjust the shims and fasteners until the unit
is square in the opening. See figure 6b.
CAUTION: Proper shimming is extremely
important. Under−shimming or over−
shimming will result in bowed jambs and
or head jamb. Both conditions can contribute to
improper window operation and performance.
Installation Tip:
method to ensure that the unit is installed
square is to check the reveal (gap) between the
operating sash and the frame. An even reveal around
the entire sash generally indicates a correctly
installed unit and will ensure smooth operation.
6. Complete shimming and fastening at locations and
spacing specified in the "Jamb/Sill Screw Chart".
See figure 6c.
7. Recheck the diagonals one more time to make sure
the unit is square in the opening. Adjust fasteners as
necessary to bring to square.
8. Once the unit is installed square and plumb, operate
the sash (on operable units) to make sure it is operat-
ing properly. If not, you may have to make some addi-
tional adjustments to the shims and fasteners.
9. If removed, replace your stops, covers, and liners.
7