Figure 65 Module Start-Up Procedures Screen - Liebert 1000kVA Operation & Maintenance Manual

100-1000kva, 60hz three phase multi-module
Table of Contents

Advertisement

Figure 65 Module start-up procedures screen

SELECT :
Select the Walk-In screen on the LCD.
Step 3. To energize the UPS module, manually close the input circuit breaker (CB1, Figure 8). This
will provide power to the rectifier. Use the Walk-In screen to monitor the Module DC Bus voltage.
WARNING
!
If any abnormal situation occurs during this walk-in procedure, open the input circuit breaker
and investigate the problem. Each input amps bar should be within 25% of the average bar
length. Call Liebert Global Services if you need help.
The Input Amps bars should settle at 25% or less after the momentary inrush current has subsided.
Verify that the DC Voltage bar begins to gradually move to the right.
Verify that the Output Voltage bar moves to the right after the DC Voltage bar has reached the 90%
level. Both bars should settle near the 100% line.
Select the Monitor/Mimic display from the Master Menu and confirm that the module DC bus and
AC output are at their proper operating voltages.
Step 4. When the Module DC Bus voltage is at 100%, you can manually close the module battery dis-
connect (MBD) circuit breaker (external to the UPS).
DOWN :
NEXT PAGE
MASTER MENU
START-UP PROCEDURES
1.
Verify that the control power is applied to the system control cabinet (check the display
on the system control cabinet).
2.
Wait approximately two (2) minutes before attempting any other action .
3.
Select "SYSTEM CONFIGURATION" screen to verify that the correct model is
displayed.
4.
Select "WALK-IN" screen and do the following:
a)
Close module input circuit breaker. Verify that the DC voltage bar on
the display begins to gradually move to the right and the AC input
current bars do not move to the right more than 10% (40% for modules
with input filters) after the transformer inrush has subsided.
UP :
FIRST PAGE
SELECT :
MASTER MENU
START-UP PROCEDURES (Cont'd)
b)
Verify that the output voltage bar moves to the right after the DC
bus bar has reached the 90% point. Both bars should settle near
their respective 100% levels.
c)
If anything happens on the display not mentioned in (a) or (b),
immediately open the module input circuit breaker and investigate.
5.
If step 4 is successful, select "MONITOR/MIMIC" screen and verify module
DC bus and output voltages are at proper nominal level. If so, close
module battery circuit breaker.
6.
If no alarms are present on the "MONITOR/MIMIC" screen, the module may be
placed online by closing the module output breaker.
© 1989-2003
© 1989-2003
89
Operation

Advertisement

Table of Contents
loading

This manual is also suitable for:

Series 610

Table of Contents